When our machinery moving and crane services teams work together, good things tend to happen. It’s not every day, though, that they work on a project that has an entire city holding their breath. Before the city of Olympia could tear down an old administrative building, they had one problem: a priceless mural, commissioned in 1956, depicting Washington State’s industrial and natural resources. At 30 feet wide and 12½ feet tall, the mural needed a new home, but transporting it was going to be a major challenge.

The department hired A to B Builders, who turned to Omega Morgan’s Seattle office for help in this risky and delicate task. In all, the mural contains 150,000 small pieces of Byzantine glass and stone, adhered to a curved concrete wall. Transportation to its new home had to occur in one piece, with no natural seams allowing to deconstruction.

The Challenge: Low Clearance and Weak Floors

In preparing for the project, our team discovered two major challenges. First, the mural was just barely shorter than the opening through which it had to fit to exit the building. Taking it apart was not an option, nor was the typical wheels to move it forward. Another solution had to be found.

Second, the 30,000 pound mural was heavier than the floors upon which it had to be transported could potentially support. Any movement within the building had to include a solution to make sure that the ground could support the move without potentially damaging the artwork.

Compared to these two major challenges, the rest of the planning was straightforward. The roads on which the transport would occur had to be shut down to avoid interference. Finally, the crane pick outside the building had to include support at 12 points instead of the usual 3 or 4 to avoid stretching or warping the mural.

The Process: Leveraging Air Skates and Shoring Work

In anticipation of potential floor support issues, Omega Morgan worked with engineering firm Associated Consultants to calculate how much load the flooring could actually hold. Based on that calculation, our team shored the lower level with 100 shoring poles and about 30 I-beams.

The clearance presented more problems that could only be solved with careful planning. After analyzing images and dimensions of the mural, our team decided on 12 low-profile air skates to move it without adding too much height. That brought total height of the mural within its frame to 12 ft 4.75 inches, leaving just about an inch clearance from the ceiling. As an additional benefit, the number of air skates transferred the weight evenly to avoid damage to the curved mural and its 150,000 tiles.

The team filed two permits with the city to clear the roads for the move itself. Finally, for the pick we leveraged a Grove GMK 5275 crane with 12 points to lift up the mural in its frame and set it safely to transport to its new location.

The Result: A Flawless Move with Local Coverage

In total, Omega Morgan worked for two days to achieve resounding success. The mural and all its 150,000 individual tiles were transported safely, without a single break or shift. A to B Builders were able to fulfill their contract to full satisfaction. Now, the city of Olympia can continue to pride itself in this priceless piece of art.

The move was so unusual that it received local press coverage in multiple outlets. A local radio station covered the move from the start, while Fiber One News built a television segment around the mural’s journey to its new home. We’re happy to help the State of Washington in preserving its art, and proud of our team’s experience and expertise that helped make this challenging move flawless.

Case Studies | Machinery Moving

Machinery Moving Excellence in Dallas

Industry Manufacturing

Equipment Used 2 15k forklifts, 8k forklift, 75-ton rough terrain crane, 75-ton truck crane, 60/80 & 40/60 Versa-Lifts

Description With a crew of 21, Omega Morgan’s Dallas machinery moving team provided diligent support for a battery energy storage company. The crew spent nine days unloading and rough-setting equipment for installation as well as assembling and installing four 14,000-pound equipment pieces in the customer’s facility.

Full Case Study

Case Studies | Machinery Moving

Moving On Up: Omega Morgan's Machinery Moving Division Provides Heavy Machinery Movers In A Flight Conveyor Upgrade

Industry Pride Recycling Company / waste processing facility

Equipment Used Versa-Lift, Rover, Telehandler All-Terrain forklifts

Description Omega Morgan’s machinery moving division facilitated a conveyor system upgrade at a waste processing facility in Oregon. The project involved moving a 40,000-pound, 65-foot long existing flight conveyor to make space for an additional 38-foot, 30,000-pound horizontal conveyance system. Omega Morgan’s trusted and reliable expertise helped to complete this project ahead of schedule and at a lower cost to their customer.

Full Case Study

Case Studies | Machinery Moving

Out with the Old: Removing and Replacing a Massive Autoclave in Arlington WA

Industry Manufacturing

Equipment Used Tri-lifter, jack and skate system, and SPMT.

Description In the process of upgrading its manufacturing equipment, a telephone pole pressure treating manufacturer needed a full-service company to remove a 160,000-pound autoclave before transporting and installing a new 230,000-pound autoclave in the same place. Omega Morgan’s Seattle machinery moving crew, with support from the specialized transportation and crane teams, delivered a turnkey solution.

Full Case Study

Case Studies | Machinery Moving

Long-Term Machinery Moving: Relocating Over 115 Spindle Machines

Industry Manufacturing

Equipment Used Forklifts: 15K, Hoist 40/60, and Versilift 60/80. Tractors: 3 and 4-axle trucks along with lowboy, step deck, and double drop trailers

Description Relocating to a facility in Lakewood, WA, a manufacturer needed a machinery moving team that could deliver expertise and flexibility over a long time period, without costing production value. Over a year and a half later, Omega Morgan has transported the majority of the components, including 115 spindle machines, while continuing to move one load a week as the job wraps up.

Full Case Study

Case Studies | Machinery Moving

A Speedy Swap: Replacing Three 380,000-Pound Transformers in Seven Days

Industry Power

Equipment Used 6-line Self Propelled Modular Transporters (SPMT). 4 100-Ton Computer Controlled Synchronized Jacking Gear. 200 feet of skid beams and 300-ton skid shoes with a push-pull system

Description After one of its three active transformers failed, a Centralia power generation station realized it needed to swap all three transformers for new components. To avoid the impending power shortage, Omega Morgan’s Seattle machinery moving team swapped the transformers—each weighing 380,000 pounds—in seven days.

Full Case Study

Case Studies | Machinery Moving

The Complete Solution: Storing & Setting Two Air Handlers in Bellevue WA

Industry Construction

Equipment Used Tri-Lifter

Description With construction underway on a new, mixed-use office building in downtown Bellevue, Washington, the builders needed two large air handlers placed — a task that would require skilled heavy lift operators. Omega Morgan not only provided expert machinery moving services, but the complete solution by storing the air handlers in Fife prior to installation. Overcoming height restrictions and other challenges, the machinery moving team delivered a world-class solution.

Full Case Study

Case Studies | Machinery Moving

Special Delivery: Moving Metal Fabrication Equipment in Boise ID

Industry Metal Fabrication

Equipment Used Hoist FR 40/60 forklift

Description When a metal fabrication company was in a bind with an equipment delivery, Omega Morgan’s Boise-based machinery moving crews mobilized to make sure the delivery was a success.

Full Case Study

Case Studies | Machinery Moving

A Toast to More Capacity: Installing New Equipment at Woodinville Whiskey Distillery

Industry Food and Beverage

Equipment Used 60-ton boom trucks, Hyster S155 forklifts, Liebherr 160-ton crane

Description A distillery in Woodinville, Washington, wanted to increase their production capacity. This meant installing a whole new set of equipment in a very tight area. Enter our machinery moving team, ready to assist Wilcox Construction in this exciting new upgrade.

Full Case Study

Case Studies | Machinery Moving

In a Tight Spot: Removing a 55 000 Pound Transformer with the Riggers 120

Industry Energy

Equipment Used Riggers 120 Forklift

Description Live voltage and limited access made removal of a 55,000 pound substation transformer a complicated task without cutting power to many clients. Luckily, our Portland machinery moving crew had just the right solution to keep the lights on and move the transformer safely.

Full Case Study

Case Studies | Machinery Moving

The Total Package: Moving and Storing 15,000 square feet of Equipment for a Plant Overhaul

Industry Food Packaging

Equipment Used Tandem Trilifters, Versa lifts, Forklifts

Description When food packaging giant Crown Holdings needed serious work done at one of their packaging plants, Omega Morgan’s specialized transportation, crane services, millwrighting, machinery moving and industrial storage crews all stepped in to provide a total service solution.

Full Case Study

Case Studies | Machinery Moving

Need a Lift? Replacing Bearing Pads in a Parking Garage in Downtown Portland

Industry Construction

Equipment Used (1) 100-ton jacking system, (1) fabricated steel base

Description Omega Morgan’s machinery moving crews fabricated an efficient engineering solution to replace bearing pads in a damaged parking deck in downtown Portland.

Full Case Study

Case Studies | Machinery Moving

Lift and Drift: A Unique Solution for Installing Power Skids at the JE Dunn Data Center

Industry Manufacturing

Equipment Used (1) 200-ton crane, rolling blocks, chain falls, skates

Description Using a not-often-seen technique that aided with both space and cost savings, Omega Morgan’s Portland-based machinery moving crews assisted with the installation of power skids at the JE Dunn Data Center in Hillsboro, OR.

Full Case Study

Case Studies | Machinery Moving

Overhead Crane Swap at a McMinville Steel Mill

Industry Steel

Equipment Used gantry, hydraulic turntable, forklifts, manlifts

Description Omega Morgan’s Portland-based machinery moving crew executed the move of two, 27.5 ton-capacity overhead double girder bridge cranes for a steel mill in McMinville, OR. The move needed to be completed with minimal disruption to mill operations. Our crew meticulously planned and successfully completed the move, working with only seven inches of clearance and 24 hours of time.

Full Case Study

Case Studies | Machinery Moving

Installing a Hot Isostatic Press in Canby, Oregon

Industry Fabricated Metal Products

Equipment Used (4) posts of a 250-ton Gantry

Description Omega Morgan’s Portland-based machinery moving crews were called upon to install the first of four Hot Isostatic Presses at a brand-new facility in Canby, OR. Faced with a unique rigging challenge and shipping delays, our crews did whatever it took to complete this tricky installation smoothly and on schedule.

Full Case Study

Case Studies | Machinery Moving

Setting up Equipment for the Northwest Machine Tool Expo

Industry Machining and Manufacturing

Equipment Used (1) 5k Forklift, (2) 8k Forklifts, (2) 15k Forklifts, (1) 30k Forklift, (1) 23/35 Versa Lift, (1) 40/60 Versa Lift & (3) Gear Trailers

Description As the official rigging provider for the NW Machine Tool Expo in Portland, Oregon, Omega Morgan’s Machinery Moving team moved 80 various machine tools into place for all of the vendor booths at this year’s event. Even with only two days to set up all the machine tools at the show, our experienced crews tackled this project with ease.

Full Case Study

Case Studies | Machinery Moving

Machinery Moving – Replacing Electrical Transformers on Vashon Island

Industry Electrical

Equipment Used 50T slide gear, 75T tri-lifter, 12K reach forklift

Description Omega Morgan’s Seattle machinery moving team worked with Puget Sound Energy to replace two old transformers and accessories at the Vashon Island Substation. This project required adapting to challenges including soft ground and a steep grade. In this case study we discuss how we found reliable solutions to successfully and safely complete the project.

Full Case Study

Case Studies | Machinery Moving

Basement Machinery Installation at Seattle Central College

Industry Electrical / Mechanical

Equipment Used 60 ton boom truck, Flatbed semi truck

Description Omega Morgan’s Seattle team was contacted by McKinstry Co., Llc to provide machinery moving services for a generator install project at Seattle Central College. In this case study we recount how our teams worked together to safely remove an old 10,000-pound CAT generator from the college’s basement and replace it with a new CAT generator weighing over 21,000 pounds. From taking out the sidewalk panels and maintaining safe operations in a busy pedestrian area, we were proud of our guys completing the project beyond customer satisfaction.

Full Case Study

Case Studies | Machinery Moving

Machinery Moving – Trolley Car Relocation

Industry Restaurant

Equipment Used Gear Rig, Machinery Moving Skates, Pneumatic 30K Forklift, Slide Rails, Jacks, 3 Axle Truck, Lowboy Trailer

Description OM crews jacked up an antique trolley car and weighed it prior to moving, so that the rigging plan would ensure that moving the car would not damage the floor in the historical building. The crew removed the trolley wheels and set the car onto rails to slide it out of the building. It was lifted and set onto the trailer for transport to its new destination. Crews offloaded the car, set it on skates, and moved it into position in the building. Upon approval, the antique trolley car came off the skates to rest in its final destination.

Full Case Study

Case Studies | Machinery Moving

Bridge Crane Machinery Project Using a TriLifter

Industry Steel Fabrication

Equipment Used Trilifter / Versalift 60/80 / Versalift 40/60

Description Bridge cranes are among the heaviest pieces of equipment in most industrial settings. In this case study we showcase how we lifted, rotated and lowered an existing bridge crane to ground level for maintenance using our Trilifter and put it back in place after the maintenance was completed. Our Steel Fabrication industry client was satisfied with the project that was on time, on budget, and completed exactly as required.

Full Case Study

Case Studies | Machinery Moving

Medical Equipment Machinery Moving at Overlake

Industry Medical Equipment

Equipment Used (2) Trilifters, (2) 15k Forklifts, Versalift 40/60, 400ft of floor protection

Description Our ability to successfully plan, manage, and finalize complicated moves was on display during the Overlake Medical Equipment Moving Project. Our team removed three MRIs and two CT scanners from the 2nd floor of the Overlake Hospital Medical Center and installed one new MRI onsite. The relocated equipment was either prepared for shipment or installed in the Medical Imaging Department on the building’s first floor.

Full Case Study

Have a Similar Project? Contact Omega Morgan