Foundation First: Installing a Dewatering Plant Foundation in Scappoose OR

INDUSTRY

Construction

EQUIPMENT USED

  • Excavator
  • 10K reach forklift
  • 60M concrete boom truck

The dredge dewatering system of a major concrete and aggregate company in Scappoose, OR, had been in the same location for several years, but dredging activities had formed a peninsula around the system. As a result, the company needed to move their entire operation half a mile away to remain in close proximity to the activity, yet out of the projected dredge path. They had planned this relocation for October, during a scheduled plant shut-down, but they needed a massive concrete foundation installed before the main system parts could be moved.

Their search for a reliable millwright company that could handle the size and scope of the project began. After providing a drawing set to our Portland-based millwright team and receiving our quote, Omega Morgan was awarded the project. With two weeks to plan the installation and four weeks for completion, our industrial millwright services team got to work.

MILLWRIGHT SERVICES FROM THE FOUNDATION UP

Planning began with an initial site survey, which provided a better understanding of the project’s size — 500-square-yards and the second-largest foundation our team has cast to date. The challenge that comes with a foundation of that size is scaling; the steps for installation remain the same as a smaller foundation, but successful completion must allow for additional time and crew members while breaking the tasks into manageable pieces.

Our millwright crew developed a strategic plan to include two concrete pours — one for the lower main pad and a second for the machine pedestals. The crew also pre-built wooden form panels during the planning process and purchased the necessary 30,000-pound rebar package. Executing the plan would involve limited equipment: an excavator for clearing and backfill, a 10,000-pound reach forklift to handle the material, and a 60M boom truck to place the concrete.

INDUSTRIAL MILLWRIGHTS AT YOUR SERVICE

With four weeks to complete the installation and 300 cubic yards of concrete to place, our team of four millwright technicians assembled. Excavating the area and setting the crushed-rock backfill support for the vast foundation occupied the first five days. Next, Omega Morgan’s millwright team placed the wooden form panels into position and installed the majority of the 30,000 pounds of rebar within the framework over four days. When the time came to place the concrete, six additional millwright professionals joined the team. Together, they made quick work of pouring, spreading, and smoothing the main concrete pad in one day, prior to tackling the machine pedestals. Our crew then formed each of the machine pedestals on top of the main foundation before installing the rebar and completing the second pour within the remaining six days. Finally, we stripped off the forms to expose the finished product.

In October, with the new machinery foundation installed on schedule, Omega Morgan helped finish the plant machinery relocation. Our client appreciated the pace at which we completed the project, as well as our attention to detail throughout the process. This project is another example of our industrial millwright crew doing the impossible daily.

Millwright Done Right: Emergency Removal of Damaged Conveyor System

Industry Agricultural Commodities

Equipment Used DB Beaver, DB Sea Horse (Hickey Marine), 60’ manlift, 40’ manlift, 12K reach lift (x2), 5K reach lift

Description When a conveyor system at Terminal 5 of the Port of Portland experienced a critical failure, Omega Morgan’s millwright services team got right on the job to quickly—and safely—repair the damage.

Full Case Study

Installing a New Rebar Storage Table for Cascade Steel

Industry Steel

Equipment Used 12K Reach Forklift, Overhead Bridge Crane

Description Omega Morgan’s millwright services team worked with speed, safety and efficiency to install a new rebar storage table for Cascade Steel Rolling Mill.

Full Case Study

Spout Removal and Rebuild at an International Grain Terminal

Industry Grain Export

Equipment Used 100 Ton Derrick Barge, material barges, 180 foot man lift, 150 foot man lift, 10K reach forklifts, machine shop

Description Our Portland-based millwright services crew was asked to assist with a damaged grain spout at Kalama Export in Kalama, WA. Our team moved fast and worked diligently to remove and rebuild the unstable spout--getting the international grain terminal back up and running quickly.

Full Case Study

Clearing a Warehouse Space in the Coffee Industry

Industry Restaurant

Equipment Used 20K warehouse forklifts, 8K warehouse forklifts, scissor lifts, man lifts, torch sets, hand tools, industrial cranes

Description As part of an acquisition of Boyd’s coffee brand and equipment, Farmer Brothers needed to remove more than 200 heavy pieces of equipment and 550 tons of recycled metals and waste from a warehouse. For help with such a complex project, they turned Omega Morgan to do the job quickly and effectively.

Full Case Study

Returning a Portland Warehouse to its Original State

Industry Solar

Equipment Used 30K warehouse forklifts, 15K warehouse forklift, IC-200 Broderson Carry Deck, 40’ Manlifts, Excavator & Hoe-ram, 35 Ton Boom Truck

Description Omega Morgan’s Millwright team helped GCL Growers move out of a warehouse in Portland. Using a variety of tools ranging from forklifts and manlifts to an excavator and a boom truck, we demolished, moved, cleaned, and even recycled. In this case study we discuss Omega Morgan’s invaluable work on this project.

Full Case Study

Moving a Suction Dredge in Scappoose Oregon

Industry Construction

Equipment Used 150 Ton Lattice Boom Crawler Crane, Grove RT760 Hydro Crane

Description Omega Morgan provided crane assistance, operators, and millwrights to help receive, assemble and move a suction dredge in Scappoose, Oregon. Our teams worked with CalPortland and Dredging Supply Company to safely and efficiently assemble and move this nearly two million pound apparatus from land to water. In this case study we explain Omega Morgan’s work in this two-month assembly and colossal move.

Full Case Study

Ship Loader Grain Delivery Spout

Industry Grain / Port

Equipment Used Derrick Barge Crane, Tugging Service, Scaffolding Service, (1) 150’ Manlifts, Welders

Description Omega Morgan’s Portland- Millwright Services Division was contacted by Kalama Export, an international grain terminal in Kalama, WA to fix an underperforming articulating grain spout. The complex fix required an ocean-going barge and tug service, scaffolding, a 150’ manlift, welders, and a derrick barge crane. In this case study we outline how our industrial millwright services crews diagnosed the problem with the spout, and safely performed a long-term solution.

Full Case Study

Cascade Steel Mill Ladle Turret Replacement Case Study

Industry Steel

Equipment Used Tadano ATF 160G (200 Ton Crane), Full Counterweight, Kamag K25 PST 10-Axle Line Towable Hydraulic Platform Trailer, T-800 Kenworth Prime Mover, Aspen 90-Ton Lowbed, Peterbilt 379 Heavy Haul Tractor

Description We partnered with Cascade Steel Mills for a major steel mill ladle turret replacement project. The steel mill ladle turret weighed 62.5 tons and we moved it nearly 200 miles from Tacoma, WA to McMinnville, OR where it was installed. In this case study we outline how we accomplished this task, what equipment we used and how we tackled the moving and installation process.

Full Case Study

Export Dock Maintenance & Millwright Services

Industry Grain Export

Equipment Used 100 Ton Barge Mounted Derrick Crane, Materials Barge, Tugboat, (2) 150’ Manlifts, 12K Reach Forklift, Diesel Welders

Description Our experienced millwright services team was asked to assist a valuable client in the Grain Export industry with installing a new catwalk during their annual dock and ship loader maintenance project. In this case study we discuss how we successfully planned the project in and amongst other projects and dependencies, and how we executed flawlessly the work within our allotted time frame.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote