Returning a Portland Warehouse to its Original State

INDUSTRY

Solar

EQUIPMENT USED

  • 30K warehouse forklifts
  • 15K warehouse forklift
  • IC-200 Broderson Carry Deck
  • 40’ Manlifts
  • Excavator & Hoe-ram
  • 35 Ton Boom Truck

Consolidating assets is not always easy, especially when closing an entire facility. That was the case last year, when GCL Growers, an international solar products company, moved out of a warehouse. In their need to return the warehouse to its original state, the company turned to the Millwright team out of our Portland office.

The task might seem simple to an outside observer: turn the facility back into an empty warehouse to be used for other purposes. The fact that the work took almost eight months to complete is a first indication of the real work required.

The demolition needed to be systematic. Productivity and efficiency were key to getting the project done, and the surrounding area – including the parking lot – had to be kept in shape. From removing foundations and restoring 4,000 square feet of warehouse floor to recovering recyclable materials, our team was up for the challenge.

The Problem: Clean Destruction at Maximum Efficiency

Demolition is, by its very nature, messy. Our task was making sure that by the time GCL Growers handed the facility back to the Port of Portland, it had to be not just cleaned out, but also in top shape. That’s daunting, considering the need to remove 45 crystal grower machines, mechanical rooms, and other equipment.

A second challenge related to the first was the fact that many of the tools typically used during this process leave significant debris, such as a cutting torch, sparking tools, and more. Our team had to stay away from these tools even as they used existing infrastructure and utilities that had to be kept in place.

The Process: Heavy Equipment and Thorough Work

A systematic approach was key from the start. Omega Morgan demolished and removed the 45 crystal grower machines as an assembly line with repeating tasks. That increased productivity and efficiency to stay on top of the timeline.

Our equipment consisted of a 30K warehouse forklift, a 15K warehouse forklift, an IC-200 Broderson Carry Deck, 40 foot manlifts, an excavator and Hoe-ram, and a 35 ton boom truck. That equipment was absolutely essential to remove not just the crystal growers but also piping, transformers, switch gear, HVAC, heat exchangers, argon tanks, generators, and roof penetrations.

To work around the existing infrastructure, the team segregated electrical and mechanical circuits from the manufacturing equipment to return the facility to warehouse condition. Meanwhile, we operated an extensive recycling program that ensured all recyclable items were recovered and not wasted.

Finally, the scope of work included a thorough repair of the parking lot, after the removal of some existing mechanical equipment and equipment pedestals had ripped up the existing concrete.

The Result: Returning a Thoroughly Cleaned Facility

In total, the process of moving our client out of the warehouse took the better part of eight months. More than 4,000 square feet of warehouse space had been cleaned, accounted for, and presented the right way. The work to get there was significant, but well worth the effort.

In the end, GCL growers was able to hand over the cleaned and empty warehouse space to the Port of Portland in shape and beyond expectation. The demolition and restoration was so complete that no sign of either our client or Omega Morgan having ever been there could be found.

This project was a perfect showcase of the versatility of our Portland office. The Millwright team had to thoroughly plan, prepare, and execute a demolition and cleaning job that left little room for error. Its thorough and flawless execution left an impression on both our client and the city to which the space belonged.

Millwright Done Right: Emergency Removal of Damaged Conveyor System

Industry Agricultural Commodities

Equipment Used DB Beaver, DB Sea Horse (Hickey Marine), 60’ manlift, 40’ manlift, 12K reach lift (x2), 5K reach lift

Description When a conveyor system at Terminal 5 of the Port of Portland experienced a critical failure, Omega Morgan’s millwright services team got right on the job to quickly—and safely—repair the damage.

Full Case Study

Foundation First: Installing a Dewatering Plant Foundation in Scappoose OR

Industry Construction

Equipment Used Excavator, 10K reach forklift, 60M concrete boom truck

Description When our client’s dredge dewatering system needed to be moved half a mile away to clear the dredging path, Omega Morgan’s millwright team installed one of our largest concrete foundation projects to date — 500 cubic yards — in less than four weeks.

Full Case Study

Installing a New Rebar Storage Table for Cascade Steel

Industry Steel

Equipment Used 12K Reach Forklift, Overhead Bridge Crane

Description Omega Morgan’s millwright services team worked with speed, safety and efficiency to install a new rebar storage table for Cascade Steel Rolling Mill.

Full Case Study

Spout Removal and Rebuild at an International Grain Terminal

Industry Grain Export

Equipment Used 100 Ton Derrick Barge, material barges, 180 foot man lift, 150 foot man lift, 10K reach forklifts, machine shop

Description Our Portland-based millwright services crew was asked to assist with a damaged grain spout at Kalama Export in Kalama, WA. Our team moved fast and worked diligently to remove and rebuild the unstable spout--getting the international grain terminal back up and running quickly.

Full Case Study

Clearing a Warehouse Space in the Coffee Industry

Industry Restaurant

Equipment Used 20K warehouse forklifts, 8K warehouse forklifts, scissor lifts, man lifts, torch sets, hand tools, industrial cranes

Description As part of an acquisition of Boyd’s coffee brand and equipment, Farmer Brothers needed to remove more than 200 heavy pieces of equipment and 550 tons of recycled metals and waste from a warehouse. For help with such a complex project, they turned Omega Morgan to do the job quickly and effectively.

Full Case Study

Moving a Suction Dredge in Scappoose Oregon

Industry Construction

Equipment Used 150 Ton Lattice Boom Crawler Crane, Grove RT760 Hydro Crane

Description Omega Morgan provided crane assistance, operators, and millwrights to help receive, assemble and move a suction dredge in Scappoose, Oregon. Our teams worked with CalPortland and Dredging Supply Company to safely and efficiently assemble and move this nearly two million pound apparatus from land to water. In this case study we explain Omega Morgan’s work in this two-month assembly and colossal move.

Full Case Study

Ship Loader Grain Delivery Spout

Industry Grain / Port

Equipment Used Derrick Barge Crane, Tugging Service, Scaffolding Service, (1) 150’ Manlifts, Welders

Description Omega Morgan’s Portland- Millwright Services Division was contacted by Kalama Export, an international grain terminal in Kalama, WA to fix an underperforming articulating grain spout. The complex fix required an ocean-going barge and tug service, scaffolding, a 150’ manlift, welders, and a derrick barge crane. In this case study we outline how our industrial millwright services crews diagnosed the problem with the spout, and safely performed a long-term solution.

Full Case Study

Cascade Steel Mill Ladle Turret Replacement Case Study

Industry Steel

Equipment Used Tadano ATF 160G (200 Ton Crane), Full Counterweight, Kamag K25 PST 10-Axle Line Towable Hydraulic Platform Trailer, T-800 Kenworth Prime Mover, Aspen 90-Ton Lowbed, Peterbilt 379 Heavy Haul Tractor

Description We partnered with Cascade Steel Mills for a major steel mill ladle turret replacement project. The steel mill ladle turret weighed 62.5 tons and we moved it nearly 200 miles from Tacoma, WA to McMinnville, OR where it was installed. In this case study we outline how we accomplished this task, what equipment we used and how we tackled the moving and installation process.

Full Case Study

Export Dock Maintenance & Millwright Services

Industry Grain Export

Equipment Used 100 Ton Barge Mounted Derrick Crane, Materials Barge, Tugboat, (2) 150’ Manlifts, 12K Reach Forklift, Diesel Welders

Description Our experienced millwright services team was asked to assist a valuable client in the Grain Export industry with installing a new catwalk during their annual dock and ship loader maintenance project. In this case study we discuss how we successfully planned the project in and amongst other projects and dependencies, and how we executed flawlessly the work within our allotted time frame.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote