Spout Removal and Rebuild at an International Grain Terminal

INDUSTRY

Grain Export

EQUIPMENT USED

  • 100 Ton Derrick Barge
  • material barges
  • 180 foot man lift
  • 150 foot man lift
  • 10K reach forklifts
  • machine shop

After an incident damaged the #1 spout on their grain loader, Kalama Export–an international grain terminal in Kalama, WA–suddenly had an abundance of problems. In order to properly repair the spout, it would have to be completely removed, re-built and re-installed. Making matters more complicated, the spout was damaged in such a way that removing it posed a potential safety risk. And every day the spout was down, Kalama Export was losing revenue.

When they contacted our Portland-based millwright services crew, Omega Morgan was fully committed to getting Kamala Export’s loader back at capacity, as quickly as possible. We moved fast, pulling together a host of resources and an all-star team to complete this complex repair.

A Complicated and Costly Break

The first major challenge our team faced was getting the damaged spout out of the air.

The spout’s stability relied on all of the individual components being intact. It was composed of one mast section, two telescoping boom sections, discharge piping, dust control ducting and rigging and installation aids.

When it was damaged, there was very little preventing the spout from falling out of the air. Before we could do anything, Omega Morgan first had to consult with engineering crews to determine how to stiffen and brace the spout so it could be removed in a safe and controlled way.

As is often the case when major equipment breaks, time was not on our side. While the spout was down, Kamala Export could only operate at three-quarters capacity. With less through-put at the terminal, there were fewer ships coming in. Revenue would continue to take a hit until the spout was up and running.

Kamala Export and our crew’s primary concern was completing this complicated removal and rebuild both safely and quickly.

The Rebuild: Working with Diligence

The complexities didn’t stop once the spout was on the ground. The rebuild was next, and we now had to decide which components of the spout could be safely and effectively re-used.

We meticulously inspected the spout from top to bottom for damage, cracks and deformations. However, there were no original designs of the spout to work with–all components that needed to be rebuilt had to be carefully reverse-engineered before fabrication.

This incident was a major insurance claim for Kalama Export. Not only did Omega Morgan rescue and rebuild the spout, we also made sure to document and track our repair efforts in a way that met the insurance adjusters’ requirements.

Great Work by a World-Class Crew

To tackle this project, we pulled together the resources of our marine crews, machine shop, and Omega Morgan Logistics.

We also called on the expertise of our fantastic subcontractors: Thompson Metal Fab, Swan Island Sheet Metal and Crescere Marine Engineering. Together, we moved fast and executed with excellence.

The incident occurred in May. The replacement spout was back up and operating in early September–and Kalama Export is very satisfied with the end result.

Millwright Done Right: Emergency Removal of Damaged Conveyor System

Industry Agricultural Commodities

Equipment Used DB Beaver, DB Sea Horse (Hickey Marine), 60’ manlift, 40’ manlift, 12K reach lift (x2), 5K reach lift

Description When a conveyor system at Terminal 5 of the Port of Portland experienced a critical failure, Omega Morgan’s millwright services team got right on the job to quickly—and safely—repair the damage.

Full Case Study

Foundation First: Installing a Dewatering Plant Foundation in Scappoose OR

Industry Construction

Equipment Used Excavator, 10K reach forklift, 60M concrete boom truck

Description When our client’s dredge dewatering system needed to be moved half a mile away to clear the dredging path, Omega Morgan’s millwright team installed one of our largest concrete foundation projects to date — 500 cubic yards — in less than four weeks.

Full Case Study

Installing a New Rebar Storage Table for Cascade Steel

Industry Steel

Equipment Used 12K Reach Forklift, Overhead Bridge Crane

Description Omega Morgan’s millwright services team worked with speed, safety and efficiency to install a new rebar storage table for Cascade Steel Rolling Mill.

Full Case Study

Clearing a Warehouse Space in the Coffee Industry

Industry Restaurant

Equipment Used 20K warehouse forklifts, 8K warehouse forklifts, scissor lifts, man lifts, torch sets, hand tools, industrial cranes

Description As part of an acquisition of Boyd’s coffee brand and equipment, Farmer Brothers needed to remove more than 200 heavy pieces of equipment and 550 tons of recycled metals and waste from a warehouse. For help with such a complex project, they turned Omega Morgan to do the job quickly and effectively.

Full Case Study

Returning a Portland Warehouse to its Original State

Industry Solar

Equipment Used 30K warehouse forklifts, 15K warehouse forklift, IC-200 Broderson Carry Deck, 40’ Manlifts, Excavator & Hoe-ram, 35 Ton Boom Truck

Description Omega Morgan’s Millwright team helped GCL Growers move out of a warehouse in Portland. Using a variety of tools ranging from forklifts and manlifts to an excavator and a boom truck, we demolished, moved, cleaned, and even recycled. In this case study we discuss Omega Morgan’s invaluable work on this project.

Full Case Study

Moving a Suction Dredge in Scappoose Oregon

Industry Construction

Equipment Used 150 Ton Lattice Boom Crawler Crane, Grove RT760 Hydro Crane

Description Omega Morgan provided crane assistance, operators, and millwrights to help receive, assemble and move a suction dredge in Scappoose, Oregon. Our teams worked with CalPortland and Dredging Supply Company to safely and efficiently assemble and move this nearly two million pound apparatus from land to water. In this case study we explain Omega Morgan’s work in this two-month assembly and colossal move.

Full Case Study

Ship Loader Grain Delivery Spout

Industry Grain / Port

Equipment Used Derrick Barge Crane, Tugging Service, Scaffolding Service, (1) 150’ Manlifts, Welders

Description Omega Morgan’s Portland- Millwright Services Division was contacted by Kalama Export, an international grain terminal in Kalama, WA to fix an underperforming articulating grain spout. The complex fix required an ocean-going barge and tug service, scaffolding, a 150’ manlift, welders, and a derrick barge crane. In this case study we outline how our industrial millwright services crews diagnosed the problem with the spout, and safely performed a long-term solution.

Full Case Study

Cascade Steel Mill Ladle Turret Replacement Case Study

Industry Steel

Equipment Used Tadano ATF 160G (200 Ton Crane), Full Counterweight, Kamag K25 PST 10-Axle Line Towable Hydraulic Platform Trailer, T-800 Kenworth Prime Mover, Aspen 90-Ton Lowbed, Peterbilt 379 Heavy Haul Tractor

Description We partnered with Cascade Steel Mills for a major steel mill ladle turret replacement project. The steel mill ladle turret weighed 62.5 tons and we moved it nearly 200 miles from Tacoma, WA to McMinnville, OR where it was installed. In this case study we outline how we accomplished this task, what equipment we used and how we tackled the moving and installation process.

Full Case Study

Export Dock Maintenance & Millwright Services

Industry Grain Export

Equipment Used 100 Ton Barge Mounted Derrick Crane, Materials Barge, Tugboat, (2) 150’ Manlifts, 12K Reach Forklift, Diesel Welders

Description Our experienced millwright services team was asked to assist a valuable client in the Grain Export industry with installing a new catwalk during their annual dock and ship loader maintenance project. In this case study we discuss how we successfully planned the project in and amongst other projects and dependencies, and how we executed flawlessly the work within our allotted time frame.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote