Cascade Steel Mill Ladle Turret Replacement Case Study

INDUSTRY

Steel

EQUIPMENT USED

  • Tadano ATF 160G (200 Ton Crane)
  • Full Counterweight
  • Kamag K25 PST 10-Axle Line Towable Hydraulic Platform Trailer
  • T-800 Kenworth Prime Mover
  • Aspen 90-Ton Lowbed
  • Peterbilt 379 Heavy Haul Tractor

In February 2018, Omega Morgan partnered with Cascade Steel Mills for a major steel mill ladle turret replacement project. Our goal was to move a ladle turret weighing 62.5 tons from Tacoma, WA to McMinnville, OR, and install it on site.

A ladle turret is a crucial part of any steel mill. It holds and rotates two hot metal ladles of steel that feed a continuous steel casting system. For this project, installation precision was as important as moving the 62.5-ton oversized load nearly 200 miles from the port of Tacoma to the mill in McMinnville.

The First Stage: Precision & Power in Steel Mill Ladle Turret Movement & Preparation

The client relied on us to receive the new equipment at the Port of Tacoma. Through our Specialized Transport capabilities, we were able to transport the steel mill ladle turret to the site at McMinnville without incident. At the same time, the old equipment onsite required removal before we could install its new counterpart.

The transport arrived one week before the scheduled installation, so beginning on Saturday, Omega Industrial Services worked around the clock. They disassembled the old turret, assisted an onsite team in relocating the unit outside, and brought the new turret into the building. To accomplish this, we used a 200-ton crane to move the outdated equipment outside while installation preparation for the new unit continued inside the building.

The Second Stage: Overcoming Obstacles in the Steel Mill Ladle Turret Installation

During the restoration process, the team discovered unexpected cracks in the supporting steel structure of the machine. Left unaddressed, these cracks had the potential to compromise the integrity and safety of the entire mill. That’s where our expertise in these types of projects became crucial. Omega Morgan quickly deployed the needed resources to overcome the obstacle in under 24 hours. The turnaround and fix was fast enough to avoid any significant project delays.

Another challenge involved preparing the surface for mounting a large rotating bearing. Our field machining services were deployed to restore a machined surface, 6 inches wide around a circle approximately 120 inches diameter (approximately 2,300 square inches).

The Result: Successful Installation and Future Prospects

Thanks to the experience of our crew, Omega Morgan was able to complete the install to within half the manufacturers recommended tolerances (.005”). The 0.005″ tolerance showcases our team’s expertise in this type of precision work. Assembly also included post tensioning approximately 160 fasteners using our hydraulic torque wrenches.

The final result significantly benefits Cascade Steel Mills. The newly installed steel mill ladle turret will hold and rotate two 30-ton hot metal ladles, which will be able to contain up to 210 tons of liquid steel at 3,000 degrees Fahrenheit, held at 40 feet above ground level when in operation. This will allow the mill to continually produce around 55 tons of steel per hour, to be used in products such as rods, rebar, wire, merchant billet bars, and some structural shapes.

The project also showed the added value Omega Morgan can provide to its clients. In addition to the steel mill ladle turret replacement, we were able to use our line haul equipment to rig and relocate two electric arc furnace roofs weighing 50 tons each.

In short, this project showcased a versatile deployment of the resources Omega Morgan can provide. Completing this job was a combined effort, from our team members in sales, estimating, project management, and procurement, to our onsite team members performing the heavy labor. In many ways, the project embodied our mantra of Strength and Trust, which we can offer to any customers looking to haul or install heavy equipment.

Millwright Done Right: Emergency Removal of Damaged Conveyor System

Industry Agricultural Commodities

Equipment Used DB Beaver, DB Sea Horse (Hickey Marine), 60’ manlift, 40’ manlift, 12K reach lift (x2), 5K reach lift

Description When a conveyor system at Terminal 5 of the Port of Portland experienced a critical failure, Omega Morgan’s millwright services team got right on the job to quickly—and safely—repair the damage.

Full Case Study

Foundation First: Installing a Dewatering Plant Foundation in Scappoose OR

Industry Construction

Equipment Used Excavator, 10K reach forklift, 60M concrete boom truck

Description When our client’s dredge dewatering system needed to be moved half a mile away to clear the dredging path, Omega Morgan’s millwright team installed one of our largest concrete foundation projects to date — 500 cubic yards — in less than four weeks.

Full Case Study

Installing a New Rebar Storage Table for Cascade Steel

Industry Steel

Equipment Used 12K Reach Forklift, Overhead Bridge Crane

Description Omega Morgan’s millwright services team worked with speed, safety and efficiency to install a new rebar storage table for Cascade Steel Rolling Mill.

Full Case Study

Spout Removal and Rebuild at an International Grain Terminal

Industry Grain Export

Equipment Used 100 Ton Derrick Barge, material barges, 180 foot man lift, 150 foot man lift, 10K reach forklifts, machine shop

Description Our Portland-based millwright services crew was asked to assist with a damaged grain spout at Kalama Export in Kalama, WA. Our team moved fast and worked diligently to remove and rebuild the unstable spout--getting the international grain terminal back up and running quickly.

Full Case Study

Clearing a Warehouse Space in the Coffee Industry

Industry Restaurant

Equipment Used 20K warehouse forklifts, 8K warehouse forklifts, scissor lifts, man lifts, torch sets, hand tools, industrial cranes

Description As part of an acquisition of Boyd’s coffee brand and equipment, Farmer Brothers needed to remove more than 200 heavy pieces of equipment and 550 tons of recycled metals and waste from a warehouse. For help with such a complex project, they turned Omega Morgan to do the job quickly and effectively.

Full Case Study

Returning a Portland Warehouse to its Original State

Industry Solar

Equipment Used 30K warehouse forklifts, 15K warehouse forklift, IC-200 Broderson Carry Deck, 40’ Manlifts, Excavator & Hoe-ram, 35 Ton Boom Truck

Description Omega Morgan’s Millwright team helped GCL Growers move out of a warehouse in Portland. Using a variety of tools ranging from forklifts and manlifts to an excavator and a boom truck, we demolished, moved, cleaned, and even recycled. In this case study we discuss Omega Morgan’s invaluable work on this project.

Full Case Study

Moving a Suction Dredge in Scappoose Oregon

Industry Construction

Equipment Used 150 Ton Lattice Boom Crawler Crane, Grove RT760 Hydro Crane

Description Omega Morgan provided crane assistance, operators, and millwrights to help receive, assemble and move a suction dredge in Scappoose, Oregon. Our teams worked with CalPortland and Dredging Supply Company to safely and efficiently assemble and move this nearly two million pound apparatus from land to water. In this case study we explain Omega Morgan’s work in this two-month assembly and colossal move.

Full Case Study

Ship Loader Grain Delivery Spout

Industry Grain / Port

Equipment Used Derrick Barge Crane, Tugging Service, Scaffolding Service, (1) 150’ Manlifts, Welders

Description Omega Morgan’s Portland- Millwright Services Division was contacted by Kalama Export, an international grain terminal in Kalama, WA to fix an underperforming articulating grain spout. The complex fix required an ocean-going barge and tug service, scaffolding, a 150’ manlift, welders, and a derrick barge crane. In this case study we outline how our industrial millwright services crews diagnosed the problem with the spout, and safely performed a long-term solution.

Full Case Study

Export Dock Maintenance & Millwright Services

Industry Grain Export

Equipment Used 100 Ton Barge Mounted Derrick Crane, Materials Barge, Tugboat, (2) 150’ Manlifts, 12K Reach Forklift, Diesel Welders

Description Our experienced millwright services team was asked to assist a valuable client in the Grain Export industry with installing a new catwalk during their annual dock and ship loader maintenance project. In this case study we discuss how we successfully planned the project in and amongst other projects and dependencies, and how we executed flawlessly the work within our allotted time frame.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote