Clearing a Warehouse Space in the Coffee Industry

INDUSTRY

Restaurant

EQUIPMENT USED

  • 20K warehouse forklifts
  • 8K warehouse forklifts
  • scissor lifts
  • man lifts
  • torch sets
  • hand tools
  • industrial cranes

Acquisitions often require complex operational adjustments, and many don’t realize that they can also mean major physical work, as the businesses undergo substantial changes.

When Farmer Brothers purchased the Boyd’s brand last year, the Texas-based coffee distributor turned to Omega Morgan’s Portland office for assistance. They needed help in removing more than 200 heavy pieces of equipment and 550 tons of recycled metals and waste from a warehouse, and clearing out the space needed to happen in a very short time period.

Farmer Brothers had purchased the coffee brand and equipment, but Boyd’s retained ownership of the building. That meant clearing out this major space within 10 weeks, to avoid substantial potential penalties for lost rent.

Fortunately, the Omega Morgan millwright team was up to the task.

The Project: A Major Millwright Job on a Tight Timeline

Omega Morgan was slated to provide all labor, equipment, materials, and services to Farmer Brothers in order to completely clear their warehouse in Portland, which would ultimately be retained by the Boyd’s Family. The warehouse was filled with:

  • More than 200 pieces of equipment, equivalent to 12 truckloads, that would be saved for re-use by Farmer Brothers. Equipment pieces ranged from blenders, coffee grinders, carton erectors, and food bagging machines to a number of other pieces commonly used in the coffee industry.
  • Approximately 400 tons of recycled metals from obsolete equipment, mezzanines, and ducting.
  • Approximately 150 tons of office and warehouse waste to completely clear out.

Any equipment left in the warehouse on January 1, 2019 (10 weeks after the start of the job) would result in Farmer Brothers needing to pay Boyd’s a penalty for lost rent. Along with an already tight timeline, Omega Morgan also navigated a changing scope which made the job even more complex, as the building had to be modified as a result of the equipment no longer existing in that space.

The Process: Close Cooperation and Simultaneous Work

Despite the deadline and the changing scope, the Omega Morgan team worked quickly and diligently. The warehouse space was divided up into multiple spaces, which allowed Omega Morgan to send in multiple crews and work simultaneously to remove equipment and load the trucks. This included removing the equipment in pieces that were as large as possible to minimize the overall effort and potential delays in the field.

The team also developed a system of tagging, cataloging, and tracking so that all items would be saved, transported, and scrapped to optimize efficiency. The actual move occurred with the help of 20K and 8K forklifts as well as scissor lifts, man lifts, torch sets, industrial cranes, and a variety of hand tools.

Finally, Omega Morgan worked closely with Global Electric for any wiring needs, ensuring the safety of the staff and the equipment throughout the job. Omega Morgan also leveraged its partnership with Rivergate Scrap Metal, which ensured that the recycled materials would go to the scrapping facility as efficiently as possible.

The Solution: A Clean Warehouse, Ahead of Deadline

As a result of the comprehensive clearing system and close partnerships, Omega Morgan successfully completed this job. Omega Morgan cleared the warehouse four days ahead of schedule, ensuring that Boyd’s could rent out the facility and Farmer Brothers would not need to pay a penalty.

The job was completed despite the changing scope and remained on budget, a testament to the experience of the Omega Morgan Portland crew. The tagging system created, and the ability to work simultaneously in multiple areas of the warehouse, were absolutely essential in getting the job done right and ahead of time.

Omega Morgan stepped in to help ensure that the physical warehouse space would not complicate the acquisition process. With the physical warehouse space cleared out, the Boyd’s family and Farmers Brothers can move forward successfully, and both parties met the terms of their agreement.

Millwright Done Right: Emergency Removal of Damaged Conveyor System

Industry Agricultural Commodities

Equipment Used DB Beaver, DB Sea Horse (Hickey Marine), 60’ manlift, 40’ manlift, 12K reach lift (x2), 5K reach lift

Description When a conveyor system at Terminal 5 of the Port of Portland experienced a critical failure, Omega Morgan’s millwright services team got right on the job to quickly—and safely—repair the damage.

Full Case Study

Foundation First: Installing a Dewatering Plant Foundation in Scappoose OR

Industry Construction

Equipment Used Excavator, 10K reach forklift, 60M concrete boom truck

Description When our client’s dredge dewatering system needed to be moved half a mile away to clear the dredging path, Omega Morgan’s millwright team installed one of our largest concrete foundation projects to date — 500 cubic yards — in less than four weeks.

Full Case Study

Installing a New Rebar Storage Table for Cascade Steel

Industry Steel

Equipment Used 12K Reach Forklift, Overhead Bridge Crane

Description Omega Morgan’s millwright services team worked with speed, safety and efficiency to install a new rebar storage table for Cascade Steel Rolling Mill.

Full Case Study

Spout Removal and Rebuild at an International Grain Terminal

Industry Grain Export

Equipment Used 100 Ton Derrick Barge, material barges, 180 foot man lift, 150 foot man lift, 10K reach forklifts, machine shop

Description Our Portland-based millwright services crew was asked to assist with a damaged grain spout at Kalama Export in Kalama, WA. Our team moved fast and worked diligently to remove and rebuild the unstable spout--getting the international grain terminal back up and running quickly.

Full Case Study

Returning a Portland Warehouse to its Original State

Industry Solar

Equipment Used 30K warehouse forklifts, 15K warehouse forklift, IC-200 Broderson Carry Deck, 40’ Manlifts, Excavator & Hoe-ram, 35 Ton Boom Truck

Description Omega Morgan’s Millwright team helped GCL Growers move out of a warehouse in Portland. Using a variety of tools ranging from forklifts and manlifts to an excavator and a boom truck, we demolished, moved, cleaned, and even recycled. In this case study we discuss Omega Morgan’s invaluable work on this project.

Full Case Study

Moving a Suction Dredge in Scappoose Oregon

Industry Construction

Equipment Used 150 Ton Lattice Boom Crawler Crane, Grove RT760 Hydro Crane

Description Omega Morgan provided crane assistance, operators, and millwrights to help receive, assemble and move a suction dredge in Scappoose, Oregon. Our teams worked with CalPortland and Dredging Supply Company to safely and efficiently assemble and move this nearly two million pound apparatus from land to water. In this case study we explain Omega Morgan’s work in this two-month assembly and colossal move.

Full Case Study

Ship Loader Grain Delivery Spout

Industry Grain / Port

Equipment Used Derrick Barge Crane, Tugging Service, Scaffolding Service, (1) 150’ Manlifts, Welders

Description Omega Morgan’s Portland- Millwright Services Division was contacted by Kalama Export, an international grain terminal in Kalama, WA to fix an underperforming articulating grain spout. The complex fix required an ocean-going barge and tug service, scaffolding, a 150’ manlift, welders, and a derrick barge crane. In this case study we outline how our industrial millwright services crews diagnosed the problem with the spout, and safely performed a long-term solution.

Full Case Study

Cascade Steel Mill Ladle Turret Replacement Case Study

Industry Steel

Equipment Used Tadano ATF 160G (200 Ton Crane), Full Counterweight, Kamag K25 PST 10-Axle Line Towable Hydraulic Platform Trailer, T-800 Kenworth Prime Mover, Aspen 90-Ton Lowbed, Peterbilt 379 Heavy Haul Tractor

Description We partnered with Cascade Steel Mills for a major steel mill ladle turret replacement project. The steel mill ladle turret weighed 62.5 tons and we moved it nearly 200 miles from Tacoma, WA to McMinnville, OR where it was installed. In this case study we outline how we accomplished this task, what equipment we used and how we tackled the moving and installation process.

Full Case Study

Export Dock Maintenance & Millwright Services

Industry Grain Export

Equipment Used 100 Ton Barge Mounted Derrick Crane, Materials Barge, Tugboat, (2) 150’ Manlifts, 12K Reach Forklift, Diesel Welders

Description Our experienced millwright services team was asked to assist a valuable client in the Grain Export industry with installing a new catwalk during their annual dock and ship loader maintenance project. In this case study we discuss how we successfully planned the project in and amongst other projects and dependencies, and how we executed flawlessly the work within our allotted time frame.

Full Case Study