Omega Morgan is a big proponent of efficiency. Especially when new equipment needs to be installed, we step up and work hard for our clients to get them up and running as fast and safely as possible. The Cascade Steel Rolling Mill in McMinnville, OR specializes in the production of rebar, and they were in the process of installing a new rebar storage table.

Before the install, the steel mill contacted our millwright services team out of Omega Morgan’s Portland office. Our team would need to install the new table quickly so the steel mill’s operations wouldn’t be interrupted for a long period of time.

It was a job that was right up our efficiency alley. Our millwright services team went into action on this two-phased installation.

BREAKING IT DOWN AND BUILDING IT UP

In the first phase of the installation process, we worked to build the first half of the new storage table alongside the existing one. This was necessary to allow the existing table to stay in operation as long as possible. Omega Morgan coordinated with the mill during this time to facilitate the installation process, all while mill operations were still ongoing.

Then it was go-time for installation: the mill would shut down, and during that time our team would need to demo the existing rebar storage table, install the foundation for the new table, and install the table’s components as fast as possible. Our team was committed to completing this work quickly and efficiently so the mill’s operations could resume.

Our team set 700 cubic yards of concrete with 300 embed anchors and 70,000 pounds of rebar.

A BIG JOB AND A TIGHT TURNAROUND

The size of this project was unique; the foundation for the new table was 50 feet wide and 180 feet long, requiring 300 embed anchors to be precisely set and located.

Our excellent millwright services team completed this rebar storage project on time, with no accidents. We’re happy to say that the new storage table is fully operational, and Cascade Steel is already benefiting from its use.

We are grateful to have the opportunity to work with Cascade Steel Rolling Mill on this project and are proud of our team for a finely-executed job well done.

Millwright Done Right: Emergency Removal of Damaged Conveyor System

Industry Agricultural Commodities

Equipment Used DB Beaver, DB Sea Horse (Hickey Marine), 60’ manlift, 40’ manlift, 12K reach lift (x2), 5K reach lift

Description When a conveyor system at Terminal 5 of the Port of Portland experienced a critical failure, Omega Morgan’s millwright services team got right on the job to quickly—and safely—repair the damage.

Full Case Study

Foundation First: Installing a Dewatering Plant Foundation in Scappoose OR

Industry Construction

Equipment Used Excavator, 10K reach forklift, 60M concrete boom truck

Description When our client’s dredge dewatering system needed to be moved half a mile away to clear the dredging path, Omega Morgan’s millwright team installed one of our largest concrete foundation projects to date — 500 cubic yards — in less than four weeks.

Full Case Study

Spout Removal and Rebuild at an International Grain Terminal

Industry Grain Export

Equipment Used 100 Ton Derrick Barge, material barges, 180 foot man lift, 150 foot man lift, 10K reach forklifts, machine shop

Description Our Portland-based millwright services crew was asked to assist with a damaged grain spout at Kalama Export in Kalama, WA. Our team moved fast and worked diligently to remove and rebuild the unstable spout--getting the international grain terminal back up and running quickly.

Full Case Study

Clearing a Warehouse Space in the Coffee Industry

Industry Restaurant

Equipment Used 20K warehouse forklifts, 8K warehouse forklifts, scissor lifts, man lifts, torch sets, hand tools, industrial cranes

Description As part of an acquisition of Boyd’s coffee brand and equipment, Farmer Brothers needed to remove more than 200 heavy pieces of equipment and 550 tons of recycled metals and waste from a warehouse. For help with such a complex project, they turned Omega Morgan to do the job quickly and effectively.

Full Case Study

Returning a Portland Warehouse to its Original State

Industry Solar

Equipment Used 30K warehouse forklifts, 15K warehouse forklift, IC-200 Broderson Carry Deck, 40’ Manlifts, Excavator & Hoe-ram, 35 Ton Boom Truck

Description Omega Morgan’s Millwright team helped GCL Growers move out of a warehouse in Portland. Using a variety of tools ranging from forklifts and manlifts to an excavator and a boom truck, we demolished, moved, cleaned, and even recycled. In this case study we discuss Omega Morgan’s invaluable work on this project.

Full Case Study

Moving a Suction Dredge in Scappoose Oregon

Industry Construction

Equipment Used 150 Ton Lattice Boom Crawler Crane, Grove RT760 Hydro Crane

Description Omega Morgan provided crane assistance, operators, and millwrights to help receive, assemble and move a suction dredge in Scappoose, Oregon. Our teams worked with CalPortland and Dredging Supply Company to safely and efficiently assemble and move this nearly two million pound apparatus from land to water. In this case study we explain Omega Morgan’s work in this two-month assembly and colossal move.

Full Case Study

Ship Loader Grain Delivery Spout

Industry Grain / Port

Equipment Used Derrick Barge Crane, Tugging Service, Scaffolding Service, (1) 150’ Manlifts, Welders

Description Omega Morgan’s Portland- Millwright Services Division was contacted by Kalama Export, an international grain terminal in Kalama, WA to fix an underperforming articulating grain spout. The complex fix required an ocean-going barge and tug service, scaffolding, a 150’ manlift, welders, and a derrick barge crane. In this case study we outline how our industrial millwright services crews diagnosed the problem with the spout, and safely performed a long-term solution.

Full Case Study

Cascade Steel Mill Ladle Turret Replacement Case Study

Industry Steel

Equipment Used Tadano ATF 160G (200 Ton Crane), Full Counterweight, Kamag K25 PST 10-Axle Line Towable Hydraulic Platform Trailer, T-800 Kenworth Prime Mover, Aspen 90-Ton Lowbed, Peterbilt 379 Heavy Haul Tractor

Description We partnered with Cascade Steel Mills for a major steel mill ladle turret replacement project. The steel mill ladle turret weighed 62.5 tons and we moved it nearly 200 miles from Tacoma, WA to McMinnville, OR where it was installed. In this case study we outline how we accomplished this task, what equipment we used and how we tackled the moving and installation process.

Full Case Study

Export Dock Maintenance & Millwright Services

Industry Grain Export

Equipment Used 100 Ton Barge Mounted Derrick Crane, Materials Barge, Tugboat, (2) 150’ Manlifts, 12K Reach Forklift, Diesel Welders

Description Our experienced millwright services team was asked to assist a valuable client in the Grain Export industry with installing a new catwalk during their annual dock and ship loader maintenance project. In this case study we discuss how we successfully planned the project in and amongst other projects and dependencies, and how we executed flawlessly the work within our allotted time frame.