Specialized Transportation and Installation of Hot Isostatic Press in Albany OR

INDUSTRY

Fabricated Metal Products

EQUIPMENT USED

  • 150 ton dual lane transporter
  • 160 ton dual lane transporter
  • 125 ton dual lane transporter
  • (2) 550T cranes

Quintus Technologies’ QIH286, one of the largest Hot Isostatic Presses (HIP) in the world, was set to be installed at Stack Metallurgic’s facility in Albany, Oregon. It was a massive set of equipment, and it all needed to be offloaded at the Port of Tacoma and transported 215 miles to Albany for installation.

Due to the sheer size and volume of components, Quintus was looking at a minimum of three trips just to get the components transported to Albany. The job could be split up amongst multiple contractors, but that would only result in a longer process and a far-off installation date.

They were in need of a partner who could provide comprehensive, turnkey services–offloading, transportation, lifting and installation–to make the whole project into one single, efficient mobilization.

That’s where Omega Morgan came in. We worked with Quintus several years ago; they reached out to us and discovered our Portland-based specialized transportation, machinery moving and millwright crews could provide a full-service package. We all rolled up our sleeves and got to work.

The Long Haul

The first part of the process was to get the equipment offloaded at the Port of Tacoma. The entire machine came in by ship, and the Port hired Omega Morgan to offload the three large components. They were loaded directly onto three of our trailers: a 150-ton dual lane transporter, a 160-ton dual lane transporter, and a 125-ton dual lane transporter. Omega Morgan is the only company in the Pacific Northwest with the capacity to provide three separate trailers for a single-mobilization move like this.

There were also 21 truckloads of smaller components that needed to be coordinated and moved to the facility. After everything was in place, we began the 215-mile trip down the I-5 corridor to Albany.

An Engineered Solution

The project also required engineering to determine the safest and most efficient way to lift the three large components through an opening in the facility’s roof. Once we had a method, we realized that a special lifting fixture would be needed to complete the move–a fixture that Omega Morgan had engineered and fabricated.

To prepare for installation, our crews worked on the technical assembly of the support structure that rested at the bottom of a 20-foot pit in the floor of the facility. This involved laying out the location using our millwright services for precise alignment. Large-core drilled anchors were set, components were aligned, verified, final-set and grouted into place before the major components arrived.

Once they arrived on site, we set the major components into place using 2 of our 550-ton cranes. Our crews then offloaded and assembled the rest of the components, housing, piping and structures that were involved in the installation process.

Just The Beginning

We’re pleased to have had the opportunity to support Quintus with the move of this HIP, the largest press to be installed in the Pacific Northwest. Quintus was very happy with the end result, as were the owners of the facility.

We’re also proud of all of the Omega Morgan crews on the execution of this move, and of our ability to be the singular full-service provider of specialized transportation, machinery moving, rigging and millwright services for our client partners.

4.6 Million Pounds Safely Delivered: Heavy Equipment Hauling Across Wyoming

Industry Electric

Equipment Used 500-ton suspension trailer, hydraulic platform trailer, jack and slide

Description Omega Morgan and IRH completed a large-scale transportation project for the electric industry in Wyoming. The project involved moving seven 670,000-pound transformers from Laramie to Medicine Bow, WY. Using a 500-ton suspension trailer, hydraulic platform trailers, and a jack and slide system, the team delivered superior results.

Full Case Study

Jumping a Bridge: Omega Morgan’s Specialized Transportation Team Does The Impossible

Industry Power

Equipment Used 6-line SPMT trailer, 2 reach forklifts

Description Omega Morgan’s specialized transportation team provided an innovative solution, performing a “bridge jump” to bypass a bridge that could not support the weight of the 179,000-pound transformer they were transporting. In a display of engineering excellence, they constructed a temporary bridge and successfully completed this project for the power industry.

Full Case Study

Mining For Innovation: Transporting a Massive Mining Shovel

Industry Mining

Equipment Used 10-line self-propelled trailer

Description Omega Morgan’s Portland and Boise teams joined forces to assist the mining industry, transporting a nearly 600,000-pound mining shovel up a steep mountain road. Using innovation and experience, the specialized transportation crew safely moved the shovel, helping Omega Morgan’s customer, Simplot, save money and limit equipment downtime.

Full Case Study

Empowering Industry: Omega Morgan's Specialized Transportation Division Moves Six Transformers

Industry Energy / Power

Equipment Used 6-line SPMT 160-ton dual-lane trailer, 2 tri-drive Kenworth tractors, slide gear, 10K reach forklift

Description Omega Morgan’s specialized transportation division moved six transformers weighing nearly 300,000 pounds each from the Port of Portland to northeastern Oregon. The project is an important step in the power industry’s efforts to expand reach and increase service in the eastern region of the state.

Full Case Study

We’ve Got The Power: Moving a 315,500-Pound Transformer From Tacoma To Portland

Industry Specialized Transportation

Equipment Used Kenworth C500, 12 dolly 160-ton dual-lane trailer, Kenworth T800, 550-ton hydraulic crane, Jack and Slide system

Description Omega Morgan’s Portland specialized transportation division moved a 315,500-pound transformer using a 160-ton dual-lane trailer from Tacoma, WA to Portland,OR. Despite size and weight challenges, the team successfully completed the project by providing innovative transportation solutions and by working cohesively with government and local agencies.

Full Case Study

Transporting a 240,000 Lb Autoclave to Arlington, WA

Industry Manufacturing and Distribution

Equipment Used Kenworth T-500 tri-drive tractor and Dolly Walker Trailer (Transport), Liebherr LTM 1300-6.2 360T AT crane, Tadano ATF160G-5 200T AT crane (Loading), Riggers TL150BW Tri Lifter 75T (Offloading)

Description A pressure-treated wood manufacturing and distribution company was in the midst of an important upgrade to their autoclave. The new...

Full Case Study

Out with the Old: Transporting a New Transformer to Moscow ID

Industry Power Distribution

Equipment Used Six-Line Self Propelled Kamag Platform Trailer, Omega Morgan Dual Lane High Frame Trailer, 2000 Western Star Tridrive 550Cat, 2016 Kenworth T800 Tridrive

Description After a transformer failed at a Moscow, ID, substation, Omega Morgan’s specialized transportation team provided OTR heavy hauling for removal and delivery of a new unit. Overcoming permitting requirements, railcar delays, and engineering concerns, our crew developed an innovative solution to deliver the transformer safely and efficiently.

Full Case Study

Multi-Service Solution: Transporting a 255,000-pound transformer from the Port of Tacoma to Central Point OR

Industry Power Distribution

Equipment Used 125-Ton Dual Lane Perimeter Deck Trailer and 400-Ton Slide Gear System

Description Our customer—a logistics and freight forwarding company—had been hired to deliver a 255,000-pound transformer from overseas to a pad in Central Point, OR. Our expert specialized transportation team, with support from machinery moving and logistics, transported the transformer from the Port of Tacoma to the pad safely and efficiently.

Full Case Study

Transporting Over-Dimensional Loads from the Port of Longview to Hillsboro

Industry Technology

Equipment Used 125 and 150-ton dual-lane trailers, sixteen lines of dual-lane platform trailer

Description Nearing the end of their Hillsboro expansion, a technology company needed four over-dimensional loads transported from the Port of Longview to their new location. After ten months of planning, Omega Morgan’s Portland specialized transportation team delivered the loads on time and under budget.

Full Case Study

From Ship to Rail to Pad: Transporting a 474 500-pound transformer from the Port of Portland to Albany OR

Industry Power

Equipment Used six-line Kamag brand SPMT, 10-line platform trailer, 2002 Peterbilt Tri Drive tractor, 12k reach forklift, jack and slide gear.

Description When an international logistics company needed OTR transportation for a massive transformer, Omega Morgan’s Portland specialized transportation team came to the rescue. Our expert team delivered a multi-step heavy haul solution from the Port of Portland to a railcar and finally to the waiting pad—and all before the holiday deadline.

Full Case Study

Transporting Wind Energy Components from the Port of Vancouver to Arlington, OR

Industry Wind Power/Renewable Energy

Equipment Used Aspen and Temisko model double Schnabel

Description When a transport and logistics company faced a shrinking timeline to transport wind energy components from the Port of Vancouver to a distribution center in Arlington, OR, they called in Omega Morgan’s experienced specialized transportation team. Our crew overcame nearby construction challenges and start delays to deliver 82 components in under two months.

Full Case Study

Transporting Four Adsorber Vessels from the Port of Vancouver

Industry Industrial engineering / Manufacturing

Equipment Used 4-axle tractor, (2) specialized transportation tank trailers

Description 4 adsorber vessels needed to get from the Port of Vancouver to our yard in North Plains, OR. Enter our specialized transportation crew and our specialized tank trailers, ready for two nights of safe and efficient transportation.

Full Case Study

Passing an Impasse: Transporting a Transformer to Anaconda Montana

Industry Electrical Power Generation

Equipment Used Kenworth C500 Tractor, High Frame Trailer, Kenworth T800 Tri-Drive Tractor, 6-Line Self-Propelled Line Trailer, Jack and Slide System

Description A rail and rigging company needed to get a transformer to a site in Anaconda, Montana. The only catch? The load was too tall for the route, making it impassable. Enter our specialized transportation team, ready to figure out an expert solution to this transportation challenge.

Full Case Study

Making History: Transporting Massive Turbine Runners to Remote British Columbia

Industry Hydroelectric energy

Equipment Used 12 Dolly Dual Lane Trailer, Custom-Built Truss Tubes and Widening Beams, Custom-Built Reusable Restraint System, Jack & Slide System

Description Omega Morgan’s Canadian specialized transportation crews faced one of their biggest challenges yet: transporting six turbine runners weighing 380,000 pounds each for an historic hydroelectric infrastructure project.

Full Case Study

A Groundbreaking Transportation Solution for Wind Components

Industry Renewable Energy

Equipment Used (2) 220T Crawler Cranes, (2) 110T Crawler Cranes, Blade trailers, Shuttle line-trailers, Reach lifts, Fork lifts, Double Schnabel, Single Schnabel

Description When jammed transportation routes put a renewable energy customer in a real bind, our specialized transportations crews helped create a solution to transport the components from the Ports of Longview and Vancouver to Alberta, Canada--the first of its kind to be done in the Pacific Northwest.

Full Case Study

From Tacoma to Dakota: Loading and Transporting a Tail Gas Drum

Industry Logistics

Equipment Used (1) 100-Ton Dual Lane Loader trailer, (2) 130-ton mobile cranes: Grove 6300L-1 and Leibherr 1160

Description A logistics company called on Omega Morgan’s specialized transportation crew to assist with an important last minute project--transporting a tail gas drum from the Seattle, WA area to a refinery in Dickinson, North Dakota.

Full Case Study

Keeping Pace and Keeping Safe: Transporting Components for a New Wind Farm

Industry Wind Energy

Equipment Used (2) double Schnabel trailers, (1) single Schnabel trailer, (1) 13-axle perimeter trailer

Description Omega Morgan’s specialized transportation crews hauled tower sections for 38 new wind turbines from Longview, WA to Vail, WA.

Full Case Study

Transporting a 158,000 Pound Transformer and Slide Gear System at 500 PSF

Industry Public Utilities

Equipment Used 100 ton Dual Lane Loader trailer with (2) Tri-Tri tractors

Description Omega Morgan supported the Wildish Building Company when they took on a project to upgrade an existing powerhouse. Wildish Building Company needed to remove two transformers and then install two new larger transformers. The project also required the removal and replacement of a powerhouse deck, and, in order to comply with the limited deck loading, Omega Morgan had to design and build a runway to distribute a 158,000 pound transformer and slide gear system load to 500 PSF.

Full Case Study

Moving 22ft Ozone Tanks on a Strict Time Limit

Industry Construction

Equipment Used 11 axle perimeter deck trailer with low-profile rails, 7 axle perimeter deck tank trailer, pair of 4 axle tractors to pull

Description With only five weeks notice, Omega Morgan did the seemingly impossible: transporting (3) 22-foot wide ozone tanks over 39 miles of mostly rural land in Oregon. With narrow roads and many utilities and wires framing the route, this project definitely earned its SC&RA Hauling Job of the Year award!

Full Case Study

Heavy Transformer Transportation Near Portland, Oregon

Industry Electrical

Equipment Used 300-Ton high-frame trailer, Kenworth C500 semi, (2) Kenworth T800 semis

Description Omega Morgan’s specialized transportation team moved a 460,000 pound transformer nearly 50 miles, using a transport the length of a football field with a total weight of almost one million pounds...

Full Case Study

Moving a Tunnel Boring Machine in Seattle

Industry Heavy Civil

Equipment Used 3 dual lane trailers with low-profile rails

Description Transported (3) TBM components from Husky Stadium to JCM Northlink’s tunnel access site in downtown Seattle. All (3) hauls were made twice in (2) nights with limited hours using Omega Morgan’s dual lane trailers. The trailers were equipped with modified low-profile rails to ensure clearance under the low trolley lines and pedestrian bridges.

Full Case Study

Fight A.L.S. Tank Barge Transportation Case Study

Industry Marine

Equipment Used Hydraulic skidding system, (32) hydraulic jacks & power pack

Description We were asked to assist creating and executing the transport of the Fight A.L.S. tank barge from our customer’s build way to a dry dock where the barge could be prepared for its eventual launch. In this tank barge transportation case study we discuss the unique challenges and solutions for this project and how it was successfully completed.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote