Vessel Heavy Lift and Rigging

INDUSTRY

Chemical

EQUIPMENT USED

  • 4 Axle Tractor
  • 100-Ton Dual Lane Trailer
  • LTM 1400 Crane

Teamwork means combining the skills and capabilities of multiple groups in order to achieve a common goal and increase efficiency. In one recent heavy lift and rigging project taken on by our Portland office, Omega Morgan moved a 172,000 pound vessel from the Port of Longview to a chemical plant in Longview, WA. This heavy haul project demonstrated the ways in which Omega Morgan’s individual teams come together to accomplish even the most difficult projects.

The Problem: Heavy Haul in a Challenging Situation

Omega Morgan’s customer asked our heavy lift and rigging team to pick up a vessel from the Port of Longview, and transport it to its chemical plant in the city. One problem immediately arose: the height of the vessel would make it difficult to transport. We also had to find a way to not just transport the vessel, but also utilize our crane division to lift and set the vessel in place on a 12 foot-high pedestal at the chemical plant.

And, of course, timing mattered to the customer. Waiting to set up the crane until the transport arrived was not an option. Instead, we had to make sure that everything was ready for the vessel to be lifted immediately upon arrival.

The Process: Combining Heavy Rigging and Heavy Lift for Precision and Power

To accomplish our goals, we enlisted the help of two teams. Our Heavy Lift and Rigging Division teamed up with our Crane Division to rig, lift, and set the vessel at its destination. Both teams were well prepared for the challenges described above.

First, we configured our 100-Ton Dual Lane Trailer to a width of 18 feet, 6 inches. Doing so allowed us to account for and actually reduce the height of the vessel, a heavy haul which would have otherwise been difficult to transport for even a single mile. Once the trailer was configured, the Port of Longview directly discharged the cargo, moving it straight from the ship to our truck.

After the discharge, our heavy lift and rigging crew transported the vessel along Industrial Way to arrive at the chemical plant. During the transport, our crane crew went to work. The team positioned our LTM 1400 Crane at the facility to prepare for the lift of the vessel as soon as it arrived.

Once the trailer arrived, we backed it into position at the chemical plant. At that point, our crane team jumped into action and prepped the vessel for the lift. We moved the cargo to its final destination, a 12 foot-high pedestal, and set it in place precisely and without issue.

The Result: Combined Efforts for Complete Customer Satisfaction

As a result of the teamwork and interplay of two of our divisions, Omega Morgan was able to complete this project on time, and to the full satisfaction of the customer. Heavy rigging and lifting activities had to be uniquely coordinated to avoid any issues during the process. Through that coordination, we were able to maximize our potential and leverage our existing expertise.

The result was a resounding success. The teamwork and experience on both teams uniquely positions us to take on similar projects in the future.

Case Studies | Heavy Lift & Rigging

Connecting the City of Portland: Installing the Blumenauer Bicycle & Pedestrian Bridge

Industry Bridge/Highway

Equipment Used (2) 550 ton cranes, 360 ton crane, 550 ton (4) post gantry, 6 line SPMT with power pack, (2) 30K forklifts, (2) 12K reach lifts, (4) 60’-80’ manlifts, OM large power pack, (4) 75 ton climbing jacks, multiple racks of Ekki wood and crib ties, 24’ Ro-Ro ramps, and elephant stands

Description Addressing the need for a north/south crossing in Portland, the Blumenauer Bridge is a highly anticipated service bike/walkway for the city. Omega Morgan’s specialized transport team overcame engineering and time frame challenges to successfully install the bridge in under 55 hours.

Full Case Study

Case Studies | Heavy Lift & Rigging

Installing a Compressor and Turbine Using a 250-Ton Gantry

Industry Oil & Gas

Equipment Used Faymonville Trailer and 250 Ton Gantry System

Description One compressor and one turbine needed to be transported from Calgary, AB, to Chetwynd, BC, and placed into an already constructed building. That’s where our heavy lift and rigging team and our 250 ton gantry system came in and got the job done with precision and care.

Full Case Study

Case Studies | Heavy Lift & Rigging

Replacing a Slewing Bearing on a Radial Stacker Reclaimer During Hurricane Season

Industry Bulk Cargo

Equipment Used (1) Omega Morgan-designed hydraulic heavy lifting jacking system, (1) 30,000 pound winch system, custom rigging, load running blocks and tackle

Description Our heavy lift and rigging crews were called upon to replace a broken bearing on a massive radial stacker reclaimer at an international bulk handling port. It was already a complex job--but two major hurricanes required a whole other level of planning and preparation.

Full Case Study

Case Studies | Heavy Lift & Rigging

Sliding Into Place: Moving a Transformer at a Portland Substation

Industry Power Generation

Equipment Used Jack-and-slide system, 6-1 line SPMT

Description Omega Morgan’s heavy lift and rigging crews were tasked with moving a transformer at a Portland, OR energy substation--a move that presented a few tricky challenges.

Full Case Study

Case Studies | Heavy Lift & Rigging

Loading and Lashing a Ship Loader in Vancouver WA

Industry Agriculture

Equipment Used 1 x KMAG 6-Line SPMT, 4 x Dollies & 1 x Prime Mover

Description Omega Morgan completed the complex move of a 530,000 pound ship loader for an engineering and manufacturing firm. Our heavy lift and rigging team implemented solutions to load and lash the equipment without incident.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote