Sliding Into Place: Moving a Transformer at a Portland Substation

INDUSTRY

Power Generation

EQUIPMENT USED

  • Jack-and-slide system
  • 6-1 line SPMT

Portland General Electric (PGE) is in the midst of a substantial, 5-year project: modernizing and strengthening the energy grid in the northwest Portland area. The multi-phased project includes making upgrades to power lines and substations around the city–an important part of the plan that will help PGE continue providing reliable energy service to the area. And as the population continues to expand, this infrastructure will be critical.

As part of this project, PGE needed a transformer relocated during the rebuild of one of their substations. They called on Omega Morgan’s heavy lift and rigging crews out of Portland to assist with the move. The job ended up being a joint effort between our cross-trained heavy lift and rigging team and machinery moving specialists–a strong combination of heavy equipment movers with just the expertise needed for this relocation.

All Dressed Up With Somewhere to Go

Since PGE was planning on adding a 230 kilovolt transmission line to this substation, our crews would need to move the existing transformer to a staging area while the work to add the line was being done. Then, once the work was complete, our crews would return the transformer to its new foundation.

The transformer weighed approximately 156,000 pounds and it was left fully dressed–meaning both the radiators and bushings remained attached to the transformer. This would help cut down on time and labor costs–the accessories would not need to be reattached and the transformer would not need to be drained of oil–but it did make the transformer very wide, tall and heavy to move.

The first step was for our machinery moving crew to get the heavyweight equipment onto the staging area while the work was done to add the 230kV transmission line and pour a new foundation pad for the transformer to return to.

Bridging Over Pits and Trenches

Our heavy lift and rigging crews used a jack-and-slide system and a 6-line self-propelled modular transporter to remove the transformer, place it onto the line trailer and return it back onto the new pad. There were a few tricky spots of terrain to manage; while moving the transformer, our crews had to block out and plate over a utility trench in order to safely get across. Our heavy lift and rigging team also needed to bridge an open pit using crib ties when it was time to return the transformer to the new foundation.

In the end, our machinery moving and heavy lift and rigging services teams completed this interesting project on time, on budget, and without incident. PGE was very satisfied with the end result. Our Omega Morgan crew is grateful for the opportunity to support Portland General Electric with their efforts to create a reliable and modernized platform for the future of the area’s energy needs.

Case Studies | Heavy Lift & Rigging

Connecting the City of Portland: Installing the Blumenauer Bicycle & Pedestrian Bridge

Industry Bridge/Highway

Equipment Used (2) 550 ton cranes, 360 ton crane, 550 ton (4) post gantry, 6 line SPMT with power pack, (2) 30K forklifts, (2) 12K reach lifts, (4) 60’-80’ manlifts, OM large power pack, (4) 75 ton climbing jacks, multiple racks of Ekki wood and crib ties, 24’ Ro-Ro ramps, and elephant stands

Description Addressing the need for a north/south crossing in Portland, the Blumenauer Bridge is a highly anticipated service bike/walkway for the city. Omega Morgan’s specialized transport team overcame engineering and time frame challenges to successfully install the bridge in under 55 hours.

Full Case Study

Case Studies | Heavy Lift & Rigging

Installing a Compressor and Turbine Using a 250-Ton Gantry

Industry Oil & Gas

Equipment Used Faymonville Trailer and 250 Ton Gantry System

Description One compressor and one turbine needed to be transported from Calgary, AB, to Chetwynd, BC, and placed into an already constructed building. That’s where our heavy lift and rigging team and our 250 ton gantry system came in and got the job done with precision and care.

Full Case Study

Case Studies | Heavy Lift & Rigging

Replacing a Slewing Bearing on a Radial Stacker Reclaimer During Hurricane Season

Industry Bulk Cargo

Equipment Used (1) Omega Morgan-designed hydraulic heavy lifting jacking system, (1) 30,000 pound winch system, custom rigging, load running blocks and tackle

Description Our heavy lift and rigging crews were called upon to replace a broken bearing on a massive radial stacker reclaimer at an international bulk handling port. It was already a complex job--but two major hurricanes required a whole other level of planning and preparation.

Full Case Study

Case Studies | Heavy Lift & Rigging

Loading and Lashing a Ship Loader in Vancouver WA

Industry Agriculture

Equipment Used 1 x KMAG 6-Line SPMT, 4 x Dollies & 1 x Prime Mover

Description Omega Morgan completed the complex move of a 530,000 pound ship loader for an engineering and manufacturing firm. Our heavy lift and rigging team implemented solutions to load and lash the equipment without incident.

Full Case Study

Case Studies | Heavy Lift & Rigging

Vessel Heavy Lift and Rigging

Industry Chemical

Equipment Used 4 Axle Tractor, 100-Ton Dual Lane Trailer, LTM 1400 Crane

Description Omega Morgan transported a 172,000-pound vessel from Port of Longview to a chemical plant in Longview, WA. Our heavy lift and rigging team configured OM’s lane loader to 18’6” wide to reduce ride height of the vessel. Finally, the team lifted the vessel from our trailer and set it in place on a 12-foot high pedestal.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote