Loading and Lashing a Ship Loader in Vancouver WA

INDUSTRY

Agriculture

EQUIPMENT USED

  • 1 x KMAG 6-Line SPMT
  • 4 x Dollies & 1 x Prime Mover

An engineering and manufacturing firm hadn’t had the best of luck with transporting one of their ship loaders; on a barge trip to British Columbia, it became dislodged from lashing in rough seas, and fell partially overboard. Since it was submerged in water, it needed to return to Vancouver, WA for repair–and on the way, it was damaged again from a collision with a piling at the nearby boat launch.

Needless to say, when it was time to load and lash the ship loader back onto a barge for the return trip, they needed a heavy lift and rigging company who could complete the job without any further incidents. When they got in touch with Omega Morgan, we were confident our team’s expertise in heavy lift, rigging and transportation would be a perfect match for this complicated move.

WHEN HILLS ARE STEEP AND TIDES ARE AGAINST YOU

Once the repairs were complete, Omega Morgan’s Portland-based crew arranged for the ship loader to be moved from land to the barge.

We were met with a few challenges right off the bat. First, the approach to the barge slip was very steep–we needed to transport the loader about 1,000 feet down a gravel path to the barge slip and onto our partner-owned barge.

This steep grade wasn’t the only wrinkle. The water level in the river was much lower than usual. This put the barge deck roughly four feet lower than the bulkhead. Moving the loader safely in these tricky circumstances required extra planning and precise work. We decided to execute the move at night–that would be the point when the tides would be highest, giving us as much height to work with as possible.

EXECUTING WITH EXPERTISE

Omega Morgan’s heavy lift and rigging crews utilized hydraulic jacks with a hydraulic platform trailer and dollies to load the 530,000 pound ship loader. To accommodate the low water level, we engineered and built a wood ramp to the barge in order to make the transition safely.

We also performed a ballasting operation while we transferred the heavy load from the ground to the barge. This involved pumping water in and out of compartments on the barge to raise and lower the deck, allowing us to keep the deck at proper height with the bulkhead.

SMOOTH SAILING AHEAD

Once the ship loader was completely onto the barge, we precisely placed the cargo on predetermined marks so it would be ready for transport. We then jacked the ship loader down, and lashed it securely to the barge.

The barge left Vancouver and arrived safely at its destination, without incident, a week later.

We’re grateful to have supported our client with this complex move. Once again, our Omega Morgan heavy lift and rigging crews leveraged their sound expertise and experience to get the job done for another happy customer.

Case Studies | Heavy Lift & Rigging

Connecting the City of Portland: Installing the Blumenauer Bicycle & Pedestrian Bridge

Industry Bridge/Highway

Equipment Used (2) 550 ton cranes, 360 ton crane, 550 ton (4) post gantry, 6 line SPMT with power pack, (2) 30K forklifts, (2) 12K reach lifts, (4) 60’-80’ manlifts, OM large power pack, (4) 75 ton climbing jacks, multiple racks of Ekki wood and crib ties, 24’ Ro-Ro ramps, and elephant stands

Description Addressing the need for a north/south crossing in Portland, the Blumenauer Bridge is a highly anticipated service bike/walkway for the city. Omega Morgan’s specialized transport team overcame engineering and time frame challenges to successfully install the bridge in under 55 hours.

Full Case Study

Case Studies | Heavy Lift & Rigging

Installing a Compressor and Turbine Using a 250-Ton Gantry

Industry Oil & Gas

Equipment Used Faymonville Trailer and 250 Ton Gantry System

Description One compressor and one turbine needed to be transported from Calgary, AB, to Chetwynd, BC, and placed into an already constructed building. That’s where our heavy lift and rigging team and our 250 ton gantry system came in and got the job done with precision and care.

Full Case Study

Case Studies | Heavy Lift & Rigging

Replacing a Slewing Bearing on a Radial Stacker Reclaimer During Hurricane Season

Industry Bulk Cargo

Equipment Used (1) Omega Morgan-designed hydraulic heavy lifting jacking system, (1) 30,000 pound winch system, custom rigging, load running blocks and tackle

Description Our heavy lift and rigging crews were called upon to replace a broken bearing on a massive radial stacker reclaimer at an international bulk handling port. It was already a complex job--but two major hurricanes required a whole other level of planning and preparation.

Full Case Study

Case Studies | Heavy Lift & Rigging

Sliding Into Place: Moving a Transformer at a Portland Substation

Industry Power Generation

Equipment Used Jack-and-slide system, 6-1 line SPMT

Description Omega Morgan’s heavy lift and rigging crews were tasked with moving a transformer at a Portland, OR energy substation--a move that presented a few tricky challenges.

Full Case Study

Case Studies | Heavy Lift & Rigging

Vessel Heavy Lift and Rigging

Industry Chemical

Equipment Used 4 Axle Tractor, 100-Ton Dual Lane Trailer, LTM 1400 Crane

Description Omega Morgan transported a 172,000-pound vessel from Port of Longview to a chemical plant in Longview, WA. Our heavy lift and rigging team configured OM’s lane loader to 18’6” wide to reduce ride height of the vessel. Finally, the team lifted the vessel from our trailer and set it in place on a 12-foot high pedestal.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote