Working Fast and Staying Safe: Erecting Steel at Mirror Lake Elementary School

INDUSTRY

Construction

EQUIPMENT USED

  • 115-ton Grove TMS9000-2

The Mirror Lake Elementary School is in the midst of a major upgrade. The brand-new building is located in Federal Way, WA. It’s been designed to give the school more room, additional functionality, and the ability to be more secure. Though things were running smoothly at the beginning of construction, as often happens when unforeseen circumstances show up, the project was threatening to fall behind pace.

At that point, Evergreen Erectors contacted our crane services crew. They called on our services to help safely accelerate the steel erection at the new building, and help the general contractor get back on track with a very tight timeline.

Our Seattle-based crane division got right to it–working with unparalleled safety and efficiency is exactly in our wheelhouse.

You Can’t Control the Weather

Winter had not done any favors for this construction site. Lots of wind and rain had made for difficult conditions at the site. Sometimes it ended up halting progress altogether. As a result, the project was running three months behind schedule. This meant the timeline for getting the steel erected was extremely tight in order to get back on schedule.

Our team brought in a highly qualified crane operator and equipment to provide hook service for the Evergreen Erectors crew. Though meeting the schedule was a priority, we were committed to bringing pace without compromising any of the rigorous safety standards to which both Evergreen Erectors and Omega Morgan are fully dedicated.

Making Good Time

Our crew used a 115-ton Grove Truck-Mounted Crane to lift the steel for attachment to the building structure. It wasn’t long before the threat of another delay began to loom: the steel fabricators were battling supply and demand challenges, which often called into question the on-time delivery of the steel to the site. Despite all of the time crunches, the teamwork between Evergreen Erectors and Omega Morgan got the job done well ahead of the already tight schedule. This type of job would normally take four to five weeks. Our composite team pulled together and completed the work in three and a half weeks. No safety incidents, no compromises. Just hard and skillful work.

We’re grateful for the opportunity to serve Evergreen Erectors on this project, and match the pace for the tight turnaround time that was required. We’re happy to say that they are very pleased with the end result. It is always a pleasure to partner and work with their stellar crew.

Case Studies | Crane Services

Moving Projects Forward: Omega Morgan's Crane Services Removes Totem Poles from a Seattle Park

Industry Crane

Equipment Used Tadano AC 4.110-1 all-terrain crane with 120-ton maximum capacity

Description Omega Morgan’s Seattle crane division delicately removed two 50-foot totem poles from a park in Seattle, allowing roof construction on a parking garage below to proceed. This project required flexibility and extensive safety precautions to ensure the 40-year-old poles were removed safely. The crew successfully completed the project, allowing important city improvements to move forward.

Full Case Study

Case Studies | Crane Services

Taking the Higher Road: Omega Morgan’s Crane Services Help Elevate A Major Thoroughfare in Kent WA

Industry Transportation/Infrastructure

Equipment Used Tadano AC5.160-1 180-ton, Tadano AC4.110-1 120-ton

Description Since Washington State began working to improve the fish passageways throughout the state, many structures have been elevated or changed to adhere to new standards, including a roadway in Kent, WA. In one evening, Omega Morgan provided essential crane services to lift and place nine 63,200-pound bridge girders as part of phase one of this project.

Full Case Study

Case Studies | Crane Services

School of Moves: Omega Morgan crane services installs modular classrooms for Yelm School District

Industry Education

Equipment Used Grove GMK6300L-1 (350 US ton crane), Main boom. 24’ Tilt Bar (major), 8’13’ Husky bars (three minors).

Description When Millpond Elementary school needed two modular classrooms placed, they called Omega Morgan Seattle crane services for a safe and efficient installation.

Full Case Study

Case Studies | Crane Services

High Up Heavy Lift: Replacing Cellular Antenna Sectors on Green Mountain

Industry Cellular Communications

Equipment Used Grove GMK 6300L-1 350-ton All Terrain Crane

Description As part of a cellular communications upgrade, the tower on Washington’s Green Mountain was ready for antenna replacement. Our customer needed crane service support to remove and replace the three 1,500-pound sectors at the top of the 200-foot pole. Enter Omega Morgan’s Seattle heavy lift team with a world-class solution.

Full Case Study

Case Studies | Crane Services

HVAC Replacement: Dozens of Heavy Lifts for Seattle WA BioMedical Renovation

Industry Construction

Equipment Used Grove GMK6350L

Description To convert an office building in Seattle, WA, into a biomedical facility, the contractor had to replace the rooftop HVAC system for improved cooling and ventilation. Needing an expert heavy lift team that could handle the steep slope and lifting several large pieces on and off the roof—along with dozens of accessories—partnering with Omega Morgan’s crane services team was a no-brainer.

Full Case Study

Case Studies | Crane Services

High Rise Heavy Lift: Placing a Component on 245-foot-high Seattle Building

Industry HVAC

Equipment Used Grove 7550 550-ton mobile crane with 220,000 pounds of counterweight, Megawing, and 220 feet of luffing jib with a 22-degree offset.

Description After the tower crane assigned to a new construction in downtown Seattle had been removed, an HVAC component arrived for roof placement on the 245-foot-high building. Needing a heavy lift team that could navigate the narrow streets and permit requirements of the project, the general contractor brought in Omega Morgan’s Seattle crane services team.

Full Case Study

Case Studies | Crane Services

Crane Express: Replacing a 70-foot sign bridge over Seattle’s I-5 express lanes

Industry Transportation/Infrastructure

Equipment Used Manitowoc NBT60 truck crane

Description Our customer, a heavy machinery services company, was tasked with removing and replacing a huge highway sign bridge over Seattle’s I-5. Needing a reliable crane services team to provide heavy lift support, they contracted our Seattle crew for the job.

Full Case Study

Case Studies | Crane Services

Mountain Views: Building a 280,000-pound excavator at an active quarry in Darrington WA

Industry Heavy Machinery

Equipment Used One Grove GMK 6300L-1 350-ton hydraulic all-terrain mobile crane and one Liebherr LTM 1130 160-ton hydraulic all-terrain mobile crane.

Description Our customer, a heavy machinery services company, was tasked with building a huge excavator on-site at an active rock quarry in Darrington, WA. Needing a reliable crane services team to provide multi-crane lifts and hold the excavator pieces in place, they tapped into our Seattle crew’s expertise for the job.

Full Case Study

Case Studies | Crane Services

An Engineered Solution: Placing Five Air Handlers into a Commercial High-Rise in Seattle WA

Industry Commercial

Equipment Used GMK 6300L 350-ton crane with full CW, engineered lifting platform, and multiple OM transport trucks and trailers.

Description When a commercial high-rise in Seattle needed new air handling units placed on five floors, Omega Morgan’s crane services team stepped up to the plate. Unable to bring the large equipment up through elevators or land them directly into the building, the team used our engineered platform to develop a unique solution.

Full Case Study

Case Studies | Crane Services

History & Crane Lifts: Relocating an Antique Train Caboose in Kirkland WA

Industry Construction

Equipment Used 350-ton crane and two truck trailers

Description An antique train caboose, harkening back to an earlier time in the Pacific Northwest region, has been a fixture at Google’s Kirkland campus since 2015. With the burgeoning popularity of the Cross Kirkland Corridor, which runs through the campus, Google decided to move the caboose along the trail for use and enjoyment by the public. Omega Morgan’s Seattle crane services crew successfully relocated the 30,000-pound caboose using a 350-ton crane and two trucks.

Full Case Study

Case Studies | Crane Services

A Unique Lift: Installing a 9,000-Pound Awning in Tigard OR

Industry Construction

Equipment Used 200-ton crane

Description As part of their new ADA-compliant walkway, a local construction company looked to install a 75-foot long, 9,000-pound awning on the front of their building. The catch? It needed to be lifted flat and then held at a 7-degree angle for the welders to attach. Omega Morgan’s crane services crew successfully completed this unique lift and hold in one day.

Full Case Study

Case Studies | Crane Services

Crossing the Puyallup: Rehabilitating the Veterans Bridge in Puyallup WA

Industry Highway/Transportation

Equipment Used Liebherr 500-Ton All-Terrain Crane

Description An important bridge across the Puyallup River was nearing the end of its lifespan and needed refurbishment to remain active. Overcoming access and crane capacity challenges, Omega Morgan successfully installed four concrete beams to reinforce the bridge.

Full Case Study

Case Studies | Crane Services

The Impossible Task: Building A Temporary Bridge In A Port Angeles Rainforest

Industry Forestry

Equipment Used (1) 500-ton Liebherr Crane LTM 1400-7.1

Description When it was said building a temporary bridge over a steep ravine in a remote forest location couldn’t be done, our crane services crew stepped up to do the impossible.

Full Case Study

Case Studies | Crane Services

Setting 100,000 pounds of equipment with precision planning at Puget Sound Energy

Industry Maritime Transportation

Equipment Used Liebherr LTM1400-7.1 w/308,000# counter-weight w/Y-Guy

Description Omega Morgan’s crane services crew worked alongside McDermott International to lift, transport and set over 100,000 pounds of equipment with a dock-positioned mobile crane at Puget Sound Energy.

Full Case Study

Case Studies | Crane Services

Hospital Installs Combination Heat and Power Plant with Help from Omega Morgan

Industry Medical

Equipment Used Forklifts, Skates, Jacking System, Tractors, Trailers, 275 Ton Crane, 350 Ton Crane, 550 Ton Crane

Description Omega Morgan’s Crane Services Team worked alongside Mckinstry between July and October to help a hospital near Seattle upgrade their energy systems to realize future cost savings.

Full Case Study

Case Studies | Crane Services

Setting the 2+U Columns in Seattle

Industry Construction

Equipment Used Two 75T TL150BW Trilifters, K25 Kamag 10 line SPMT, 550T Grove GMK7550 crane with 352,700 lbs of counterweight and main boom with Mega Wing, 485T Liebherr LTM1400-7.1 crane with 308,600 lbs of counterweight and main boom

Description The Omega Morgan crane team assisted with the construction of downtown Seattle’s high-rise office building, 2+U. Omega Morgan set 20 precast tapered concrete columns while taking into consideration night-time noise restrictions, trolley wires, and other space restricting elements. This project came with a couple of hurdles to overcome, but the Omega team was up to the task.

Full Case Study

Case Studies | Crane Services

Roosevelt Kroll Tower Crane Dismantle

Industry Construction

Equipment Used 550 ton Grove GMK 7450 with 220,000lbs counterweight and megawing, 160 ton Liebherr LTM 1130-5.1 with 92,000lbs counterweight, 275 ton crane Grove GMK 5220 with 169,000lbs counterweight

Description Omega Morgan’s Seattle office assisted Hoffman Construction in dismantling a Kroll tower crane, one of Seattle’s largest cranes. Our Crane Team’s role was to supply two assist cranes for the disassembly and offload the equipment after its relocation. With safety in mind, our team was glad to play their role in making this massive project possible.

Full Case Study

Case Studies | Crane Services

Dismantling the 1818 Fairview Tower Crane

Industry Construction

Equipment Used Main Crane - Grove GMK 7450 (550 ton) with 220,000# of counter-weight and 161’ Luffing Jib, Assist Crane - National NBT60 (60 ton)

Description The Omega Morgan Crane Team assisted BNBuilders and NW Tower Crane in the construction of the new and iconic 1818 Fairview life science office building. Omega Morgan’s role included dismantling a Liebherr 550 Tower Crane and placing the building’s atrium roof and glass roof panels. From permitting and planning to safe execution and completion, our Crane Team knocked this one out of the park!

Full Case Study

Case Studies | Crane Services

Removing a One-Piece Bridge in Tacoma

Industry Construction

Equipment Used Liebherr LR1600 Crane with 217’ boom and approximately 1.25 million lbs. of counterweight

Description When Atkinson contacted Omega Morgan’s Seattle office for help removing an old bridge, our crane services team was up to the task. While keeping the bridge intact to protect rails underneath the bridge, we successfully completed the bridge move without a hitch. This case study explains how we accomplished the one-piece bridge move.

Full Case Study

Case Studies | Crane Services

Linde's 133-Foot Cold Box Move

Industry Chemical

Equipment Used CC2500 Crawler Crane, GMK 7450 Hydraulic Crane, Dual-Lane Trailers

Description In this case study crews from our Portland, Oregon- Crane Service Division performed a dual crane lift to offload a rectification cold box from an Omega Morgan dual lane trailer to a pad at the Linde project site.

Full Case Study

Case Studies | Crane Services

Crane Services Seattle Case Study: Grove GMK 5220 All Terrain Crane

Industry Construction

Equipment Used GMK 5220

Description Moving and setting a 6-section vault is a challenging undertaking in and of itself, let alone completing it in a confined downtown Seattle space at a steep pitch. In this case study we outline the challenges, the process we created to complete the project, and the successful result we had for the client.

Full Case Study

Case Studies | Crane Services

Tower Crane Services Case Study

Industry Commercial Construction

Equipment Used 485 Ton Liebherr LTM 1400-7.1 Crane with 132K lbs. of counterweight, 118’ Main Boom, 138’ Luffing Jib, 60-Ton Boom Truck (assist crane)

Description Our team was asked to provide tower crane services at the University of Washington. The job was to safely set up and erect an ECHO 550 Morrow tower crane with 260 feet of jib on the university’s campus. In this case study we discuss how we planned for this project and the equipment we used to successfully complete it.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote