Installing a Compressor and Turbine Using a 250-Ton Gantry

Industry: Oil and Gas
Project Location: Chetwynd, BC
Services Used: Heavy Lift and Rigging
Equipment Used: Faymonville Trailer and 250 Ton Gantry System
Project Type: Compressor Station Installation

Moving natural gas from production well sites to the end consumer requires compressor stations to help maintain the pressure and flow of gas through the pipeline. Our client was constructing a compressor station in Chetwynd, BC, and needed a compressor and a turbine transported and then placed into the station building. That’s when our heavy lift and rigging team was brought in to develop a solution utilizing our 250-ton gantry system.

The Challenge: Installing Equipment in a Restricted Compressor Station

The challenge presented by this situation was that these components had skids (the bases of the turbine and compression systems) that were not engineered to move into place through a doorway via jack and slide, but had to be placed by crane.

Transporting Large Industrial Equipment

The first portion of this job was transporting the compressor and turbine 950 km from our yard in Calgary, AB, to their station in Chetwynd, BC. These essential pieces of equipment had to be moved within a set schedule to align with construction timelines.

Limited Site Access

The compressor measured 21’ long by 13’ wide by 13’2” high and weighed 229,880 pounds, while the turbine measured 37′ 6” long by 13’ wide by 13’8” high and weighed 102,180 pounds.

Our heavy lift and rigging crew safely and securely loaded these substantial pieces of equipment onto our 150 ton dual-lane perimeter deck trailer and our Faymonville HighwayMAX trailer and made the several-day trek from Alberta to British Columbia.

The Solution: Precision and Heavy Lift Planning

Once the compressor and turbine arrived in Chetwynd, the challenge of placing them within the building began.

Engineered Lift Planning

Omega Morgan’s experienced heavy lift and rigging team worked together to back the unit up as far as it would allow with mere inches of extra space.

Utilizing a 250-Ton Gantry

Our engineering team had already devised a plan with the client’s project team to precision set these components using our 250-ton lift and lock gantry system.

Coordinated Rigging Operations

The crew then rigged up the components and safely lifted them off our Faymonville trailer. Each component was individually precision set using laser measurements to the pads where they would be connected to the rest of the system.

Equipment Placement

Our skilled technicians executed this process seamlessly with precision and care.

The Result: Successful Placement of Critical Equipment

Our client was very pleased with our experienced team and the equipment we used to complete this job. As the only company in Western Canada with a lift and lock gantry system, we were glad to put it to good use as part of the solution to this unique challenge including:

  • Safe installation
  • Precision placement
  • Maintaining the schedule
  • Successful commissioning support

Related Case Studies

Replacing a Slewing Bearing on a Radial Stacker Reclaimer During Hurricane Season

Industry Bulk Cargo

Equipment Used (1) Omega Morgan-designed hydraulic heavy lifting jacking system, (1) 30,000 pound winch system, custom rigging, load running blocks and tackle

Description Our heavy lift and rigging crews were called upon to replace a broken bearing on a massive radial stacker reclaimer at an international bulk handling port. It was already a complex job--but two major hurricanes required a whole other level of planning and preparation.

Full Case Study

Loading and Lashing a Ship Loader in Vancouver WA

Industry Agriculture

Equipment Used 1 x KMAG 6-Line SPMT, 4 x Dollies & 1 x Prime Mover

Description Omega Morgan completed the complex move of a 530,000 pound ship loader for an engineering and manufacturing firm. Our heavy lift and rigging team implemented solutions to load and lash the equipment without incident.

Full Case Study

Vessel Heavy Lift and Rigging

Industry Chemical

Equipment Used 4 Axle Tractor, 100-Ton Dual Lane Trailer, LTM 1400 Crane

Description Omega Morgan transported a 172,000-pound vessel from Port of Longview to a chemical plant in Longview, WA. Our heavy lift and rigging team configured OM’s lane loader to 18’6” wide to reduce ride height of the vessel. Finally, the team lifted the vessel from our trailer and set it in place on a 12-foot high pedestal.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote