For educational institutions, a reliable power source is key to a safe environment. That includes backup generators which, though bulky, are essential in most large organizations, to account for all possibilities. When construction engineering company McKinstry Co., LLC needed help in replacing a backup generator for Seattle Central College, Omega Morgan’s machinery moving guys out of Seattle were up to the task.

The Challenge: Meeting Tight Deadlines in a Confined Basement Install

The job required both thought and planning. Omega Morgan was charged with moving the old CAT generator out of the basement, lifting approximately 10,000 pounds. Then, we had to move a new generator into the same space, taking into consideration a significant weight increase. The new machinery weighed 21,477 pounds.

Limited Access to the Installation Area

The basement location of the machinery had to be accounted for, especially considering the size of the new generator.

Protecting Existing Building Infrastructure

The location of the job made matters even more complex. Seattle Central College is located between Capitol Hill and Squire Park, two of the busiest neighborhoods in the city. Any effort had to account for heavy pedestrian traffic, and required just the right permits to make sure every action was taken within the realms of expectations and legality.

Coordinating Around Construction Schedules

The installation required close coordination with the project team to complete the generator replacement while supporting the overall construction schedule.

The Solution: Careful Planning to Safely Move Equipment Into a Restricted Space

Omega Morgan worked with the city of Seattle to secure all necessary permits well ahead of time. That included street use permission for our 60-ton boom truck, as well as permission for our crane operator and 4-man rigging crew to show up early the day of the job to get a good start. We worked with McKinstry to block pedestrian traffic through barricades to ensure the safety of onlookers and passersby, and got started.

Lift Planning and Rigging Strategy

First, the crew lifted street panels off the sidewalk and set them aside for easier access. Then, we entered the basement to disconnect the old generator, lift it off the ground, and load it onto our flatbed truck to transport it offsite. The same truck also delivered the new, larger generator for installation.

Specialized Machinery Moving Techniques

Our 60-ton boom truck was perfect to lift the new generator off the flatbed, and set it into the hole in the sidewalk. The machinery was too large to fit through the same sidewalk hole in one piece, leading to disassembly into its main parts and a fly or “floating” operation. The individual pieces were still large, so Omega Morgan rigged them to be floated in at an angle designed to fit through the hole and get them below the street surface.

Coordinated Equipment Placement

During this process, our experience in moving heavy machinery became invaluable. We made sure that the generator would be empty of fuel during the move, the only way to ensure that the necessary floating angle would not damage the machinery. The special rigging designed to get just the right angle was a crucial part of the process.

The Result: Successfully Completed the Installation on Schedule

Given its location and the size of the generator, this project was undoubtedly complex. Our experience and expertise in machinery moving ensured full customer satisfaction. Omega Morgan provided McKinstry with a turnkey solution, bringing in and installing the new generator without delaying any other projects or resulting in customer wait time.

  • Safe generator removal and installation
  • Equipment positioned accurately
  • Project timeline maintained
  • Customer objectives achieved

Hard work paid off, and will continue to pay off for the students and staff of Seattle Central College for years to come. For Omega Morgan, it’s another case study showing how our expertise and experience translates into success for even the most challenging projects in the most difficult environments.

Related Case Studies

Out with the Old: Removing and Replacing a Massive Autoclave in Arlington WA

Industry Manufacturing

Equipment Used Tri-lifter, jack and skate system, and SPMT.

Description In the process of upgrading its manufacturing equipment, a telephone pole pressure treating manufacturer needed a full-service company to remove a 160,000-pound autoclave before transporting and installing a new 230,000-pound autoclave in the same place. Omega Morgan’s Seattle machinery moving crew, with support from the specialized transportation and crane teams, delivered a turnkey solution.

Full Case Study

Long-Term Machinery Moving: Relocating Over 115 Spindle Machines

Industry Manufacturing

Equipment Used Forklifts: 15K, Hoist 40/60, and Versilift 60/80. Tractors: 3 and 4-axle trucks along with lowboy, step deck, and double drop trailers

Description Relocating to a facility in Lakewood, WA, a manufacturer needed a machinery moving team that could deliver expertise and flexibility over a long time period, without costing production value. Over a year and a half later, Omega Morgan has transported the majority of the components, including 115 spindle machines, while continuing to move one load a week as the job wraps up.

Full Case Study

Installing a Hot Isostatic Press in Canby, Oregon

Industry Fabricated Metal Products

Equipment Used (4) posts of a 250-ton Gantry

Description Omega Morgan’s Portland-based machinery moving crews were called upon to install the first of four Hot Isostatic Presses at a brand-new facility in Canby, OR. Faced with a unique rigging challenge and shipping delays, our crews did whatever it took to complete this tricky installation smoothly and on schedule.

Full Case Study

Setting up Equipment for the Northwest Machine Tool Expo

Industry Machining and Manufacturing

Equipment Used (1) 5k Forklift, (2) 8k Forklifts, (2) 15k Forklifts, (1) 30k Forklift, (1) 23/35 Versa Lift, (1) 40/60 Versa Lift & (3) Gear Trailers

Description As the official rigging provider for the NW Machine Tool Expo in Portland, Oregon, Omega Morgan’s Machinery Moving team moved 80 various machine tools into place for all of the vendor booths at this year’s event. Even with only two days to set up all the machine tools at the show, our experienced crews tackled this project with ease.

Full Case Study

Have a Similar Project? Contact Omega Morgan

Get a Quote